HomeMy WebLinkAboutRes 2025-08-1802 Purchase Order for Public Works Facility ImprovementCITY OF ANNA, TEXAS
RESOLUTION NO. 0 o a 5 - 003 - I t 0
A RESOLUTION OF THE CITY OF ANNA, TEXAS, AUTHORIZING THE CITY
MANAGER TO EXECUTE A PURCHASE ORDER FOR PUBLIC WORKS FACILITY
IMPROVEMENTS TO STRUCTURED CONTRACTOR LLC, IN ACCORDANCE WITH
TEXAS LOCAL GOVERNMENT PURCHASING REQUIREMENTS, UTILIZING THE
SOURCEWELL PURCHASING COOPERATIVE THROUGH AN APPROVED JOB
ORDER CONTRACTING (JOC) METHOD. THE PURCHASE ORDER NOT TO
EXCEED ONE HUNDRED EIGHTY-EIGHT THOUSAND EIGHT HUNDRED SEVENTY-
FOUR DOLLARS ($180,662.16), INCLUDES A 10% CONTINGENCY.
WHEREAS, the City of Ana has utilized the Texas Local Government Purchasing
Cooperative through Sourcewell Job Order Contracting to obtain a proposal for the
renovation of the Public Works Facility; and
WHEREAS, the Public Works Facility requires renovations of the building to
accommodate the growing Engineering & CIP divisions. Work includes dividing walls for
additional offices, new flooring, and pain throughout; and,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ANNA, TEXAS THAT:
Section 1. Recitals Incorporated
The recitals above are incorporated herein as if set forth in full for all purposes.
Section 2. Authorization of Payment and Funding.
That the City Council of the City of Anna hereby authorizes the Interim City Manager to
execute a purchase order for Structured Contractor LLC in an amount not to exceed
180,662.16.
That funding for the renovation of the building will come from Surplus Infrastructure
Investment funds.
PASSED AND APPROVED by the City Council of the City of Anna, Texas on this I ? h
day of August 2025.
ATTEST: * * APPROVED:
THECIFYOF
Anna
City Secretary, Carrie Land , TEXAS Mayor, Pete Cain
Exhibit A
GOPOIAN(?)
Work Order Signature Document
Sourcewell EZIQC Contract No.: TX-R3-GC-052124-SCL
FNew Work Order Modify an Existing Work Order
Work Order Number.: 146114.00 Work Order Date: 08/06/2025
Work Order Title: Anna - Public Works Building Reno
Owner Name: City of Anna Contractor Name: Structured Construction LLC
Contact: Steven Smith Contact: Brant Riner
Phone: 972-924-4510 Phone: 214-444-5916
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
Sourcewell EZIQC Contract No TX-R3-GC-052124-SCL.
Brief Work Order Description:
Replace the flooring and paint interior rooms in the public works building. Also, add a couple walls and doors to divide
large offices.
Time of Performance Estimated Start Date:
Estimated Completion Date:
Liquidated Damages Will apply: 11 Will not apply:
Work Order Firm Fixed Price: $164,238.33
Owner Purchase Order Number:
Approvals
01 /
Own Date
Work Order Signature Document
Contractor Date
Page 1 of 1
B/6/2025
8/13/2025
SOPOIAN1.9
Detailed Scope of Work
To: Select a Contractor Project Manager in People From: Steven Smith
No Data Input City of Anna
No Data Input 120 W 7th Street
No Data Input, Anna, TX 75409
No Data Input 972-924-4510
Date Printed: August 06, 2025
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Brief Scope: Replace the flooring and paint interior rooms in the public works building. Also, add
a couple walls and doors to divide large offices.
71 Preliminary Revised X Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.
SCOPE OF WORK
The City of Anna
Public Works Building - Anna, TX
Public Works Building Renovation
08/05/2025
GENERAL:
This Scope of Work describes the Public Works Building Renovation Project at the Public Works Building in
Anna, TX. Public Works Building to be performed by Structured Construction LLC ("Structured") as the
general contractor. Work includes Safety/General Requirements (Div. 01), Existing Conditions (Div. 02),
Metals (Div. 05), Openings (Div. 08), and Finishes (Div. 09), Furnishings (Div. 12), Plumbing (Div. 22), and
Electrical (Div. 26). The repairs will be phased, as required, to accommodate Anna's Public Works personnel.
1.0 SCOPE OF WORK:
The scope of work to be performed by Structured includes all labor, materials, supervision, equipment,
insurance, taxes, and overhead costs necessary to perform the work described herein.
Work includes the following:
Public Works Building Renovation
Brief SOW: Demo flooring, walls, electrical, plumbing, millwork, and install all described finishes, electrical,
plumbing, etc..
Scope of Work Page 1 of 6
8/6/2025
Detailed Scope of Work Continues..
Work Order Number: 146114,00
Work Order Title: Anna - Public Works Building Reno
1.1.1 Division 01 - Safety/General Requirements:
Work includes the following:
Provide 4 - 30 yard dumpsters for debris removal from site. 4 dumpsters total.
Provide and install approximately 4152.3 square feet of 6 mil plastic to protect all of the ceilings. 4152.3
square feet total.
1.1.2 Division 02 - Existing Conditions:
Work includes the following:
Demo and dispose of approximately 1644.4 linear feet of resilient baseboard. 1644.4 linear feet total.
Demo and remove approximately 2971.5 square feet of VCT per plan. 2971.5 square feet total.
Demo and dispose of approximately 129 square feet of ceramic tile flooring in the entry way. 129 square feet
total.
Demo and remove approximately 320.8 square yards of existing carpet. 320.8 square yards total.
Demo and dispose of approximately 129 square feet of thin set for the old ceramic tile in the front entry. 129
square feet total.
Demo 2 existing door frames per plan. Salvage 1 HM frame only, dispose of the other wood frame. 2 total.
Demo and salvage of 1 existing solid core door. 1 total.
Demo and remove approximately 264 square feet of existing epoxy flooring. 264 square feet total.
Demo and remove approximately 24 square feet of countertop per plan in front lobby. 24 square feet total.
Demo and dispose of approximately 30 connectors. 30 connectors total.
Remove I lockset/door knob and salvage to reinstall on salvaged door. 1 total.
Demo and remove existing glass window. Approximately 4 square feet window 24" x 24".
Demo and remove existing countertop in men's locker room. Approximately 12 square feet total.
Demo and Remove existing 2 sinks in mens locker room. 2 sinks removed total.
Remove and reinstall base cabinets in big break room into small break room. 18 linear feet total.
Remove and reinstall upper cabinets in big break room into small break room. 18 linear feet total.
Remove and reinstall countertops in big break room into small break room. 18 linear feet total.
Demo and remove 3 - 36" wide base cabinets in small breakroom. 3 base cabinets total.
Demo and remove 1 - 48" wide base cabinet in small breakroom. 1 base cabinet total.
Demo and remove 4 - 36" wide wall cabinets in small breakroom. 4 wall cabinets total.
Demo and remove 1 - 12" wide wall cabinet in small breakroom. 1 wall cabinet total.
Demo and remove approximately 9 square feet of existing countertops in small break room area. 9 square feet
total.
Demo and remove 20 linear feet of existing copper tubing per plan in small break room. 20 linear feet total.
Demo and remove approximately 4 - 1/2" 90's per plan. 4 - 90's total.
Demo and remove approximately 2 - 1/2" copper tees in small breakroom area. 2 total.
Demo and remove 2 -'/a" angle valves in small breakroom. 2 angle valves total.
Demo and remove approximately 20 linear feet of pvc pipe in small breakroom area. 20 linear feet total.
Demo and remove 2 sinks in men's locker room. 2 sinks total.
Scope of Work Page 2 of 6
8/6/2025
Detailed Scope of Work Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Demo and remove 4 - 1/2" copper couplings in small breakroom. 4 couplings total.
Demo and remove approximately 15 electrical boxes per plan in offices, small breakroom area, and the large
breakroom area. 15 steel boxes total.
Demo and remove approximately 120 linear feet of existing 3/4" EMT per plan. 120 linear feet total.
Demo and remove approximately 600 linear feet or armored cable per plan. 600 linear feet total.
Remove and salvage approximately 8 existing light fixtures. 8 lights total.
Demo and remove 2 - 2" pvc 90's in small breakroom. 2- 90's total.
Demo and remove 1 - 2" pvc sanitary tee in small breakroom. I tee total.
Demo and remove 2 existing p-traps from men's locker room and small break room.
Demo and remove 2 - 2" wye's in small breakroom. 2 wye's total.
Demo and remove 1 - 2" cleanout tee in small breakroom. I cleanout tee total.
Demo and remove approximately 30 cubit feet of existing slab to open up the slab to run new plumbing in the
small breakroom. 30 cubit feet total.
Sawcut approximately 55 linear feet of existing concrete slab to install new plumbing in the small breakroom.
55 linear feet total.
1.1.3 Division 05 - Metals:
Work includes the following:
Provide and install approximately 40 linear feet of square tubing to be fabricated into a frame for the new
men's locker room sink. 40 linear feet total.
Provide welder to fabricate metal frame to be hung on the wall in men's locker room for new big sink.
includes installation of frame. This includes time for shop drawings/design, shop fabrication and onsite
installation onsite. 24 hours total.
1.1.4 Division 08 - Openings:
Work includes the following:
Provide and install 1 new 36" x 36" aluminum sliding glass window at lobby per plan. 1 sliding glass window
total.
Provide and install 3 doors per plan. 3 doors total.
Provide and install three 3' x T HM door frames per plan. 3 total.
Reinstall 1 salvaged lockset/door knob. 1 lockset total.
Provide and install 3 lockets per plan. 3 locksets total.
Provide and install 2 sets (3 per set) of hinges per plan. 1.5 hinges x 2 doors = 3 hinge pairs total.
1.1.5 Division 09 - Finishes:
Work includes the following:
Perform first moisture test for new LVT flooring required for flooring warranty. I primary test total.
Perform 6 moisture tests for new LVT flooring required for flooring warranty. One secondary test is required
per 1,000 square feet. 6 secondary tests total.
Provide and install approximately 3145.7 square feet of a T' self leveling underlayment for new LVT flooring.
Scope of Work Page 3 of 6
8/6/2025
Detailed Scope of Work Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
50% coverage. 3145.7 square feet total.
Demo and remove approximately 101.2 square feet of walls per plan. 101.2 square feet total.
Provide and install approximately 616.8 square feet of new metal stud walls per plan. 618.8 square feet total.
Provide and install approximately 1233.6 square feet tape, spackle and wall finish per plan. 1233.6 square feet
total. No texture will be applied to new walls, smooth finish only.
Provide and install approximately 1644.4 linear feet of new rubber baseboards throughout entire space. 1644.4
linear feet total.
Patch approximately 511 square feet of wall in various locations to prep for paint. 511 square feet total.
Provide and install approximately 1233.6 square feet Type X gypsum board per plan. 1233.6 square feet total.
Provide and install 2 coats of paint for approximately 6490 square feet on all walls inside new space per plan.
6490 square feet total.
Provide and install 1 coat of primer for approximately 6490 square feet on all walls inside new space per plan.
6490 square feet total.
Rework existing ceilings tiles to accommodate new wall that goes above ceiling in the lobby. Approximately
30 square feet total.
Rework ceiling grid in lobby at new wall that goes above ceiling. Approximately 30 square feet total.
Provide and install 1 coat primer for 2 new HM door frames per plan. 34 linear feet total.
Provide and install 2 coats paint for 2 new HM door frames per plan. 34 linear feet total.
Provide and install 1 coat primer for 2 new wood doors per plan. 2 doors total.
Provide and install 2 coats paint for 2 new wood doors per plan. 2 doors total.
Provide and install approximately 6291.3 square feet of new LVT flooring throughout the entire space. 6291.3
square feet of flooring total.
Demo and remove approximately 93.2 linear feet of transition striping per plan. 93.2 linear feet total.
1.1.6 Division 12 - Furnishings:
Work includes the following:
Provide and install one cutout for big sink in men's locker room new solid surface countertop. 1 cutout total.
Provide and install new men's locker room sink solid surface countertop end splash guard. Approximately 1
linear feet total.
Provide and install new men's locker room sink solid surface countertop. Approximately 12 square feet total.
1.1.7 Division 22 - Plumbing:
Work includes the following:
Provide and install one undermount 40" to 48" Large Workstation Kitchen Sink - Single Bowl - Reversible
Offset Drain (5LS40c) or equivalent. 1 big stainless steel sink total.
Provide and install 2 new bathroom sink faucets in men's locker room at the new big sink. 2 faucets total.
This faucet or equivalent)
Hours for plumber to rework plumbing (drains and waterlines) underneath new big sink in men's locker room.
16 hours total.
Provide and install 60 linear feet of 1/2" copper pipe for small breakroom plumbing relocation. 60 linear feet
total.
Scope of Work Page 4 of 6
8/6/2025
Detailed Scope of Work Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Provide and install twelve 1/2" copper 90's for small breakroom plumbing relocation. 12 - 90's total.
Provide and install two 1/2" copper tees for small breakroom plumbing relocation. 2 tees total.
Provide and install four 1/2" copper couplings for small breakroom plumbing relocation. 4 couplings total.
Provide and install 2 angle stop valves for breakroom relocation of plumbing. 2 valves total.
Provide and install approximately 60 linear feet of 2" DWV PVC pipe for small breakroom relocation of
plumbing. 60 linear feet total.
Provide and install four 1/2" copper caps for small breakroom plumbing relocation. 4 caps total.
Provide and install 4 - 90's for small breakroom relocation of plumbing. 4 - 90's total.
Provide and install 1 sanitary tee for small breakroom relocation of plumbing. 1 sanitary tee total.
Provide and install 2 wyes for small breakroom relocation of plumbing. 2 wyes total.
Provide and install 1 test tee with plug for small breakroom relocation of plumbing. 1 test tee total.
1.1.8 Division 26 - Electrical:
Work includes the following:
Provide and install approximately 12 new receptacles in various added walls and breakrooms. 12 receptacles
total.
Provide and install approximately 25 steel electrical boxes per plan for j-boxes above the ceiling, electrical
outlets at new walls in offices, small breakroom area, and large breakroom area. includes switches in new
offices. 25 steel boxes total.
Provide and install 5 new steel work cover for new junction boxes in ceiling space. 5 steel covers total.
Provide and install 20 mud rings on boxes for switches and receptacles per plan. 20 mud rings total.
Provide and install 3 GFI plugs for the small breakroom. 3 GFI receptacles total.
Provide and install approximately 120 linear feet of 3/4" EMT assembly. 120 feet total.
Provide and install approximately 825 feet of M/C cable required for rewiring of lights, j boxes, switches,
outlets, etc. 825 linear feet total.
Provide and install approximately 40 connectors. 40 connectors total.
Provide and install approximately 5 new switch assemblies. 5 switch assemblies total.
Provide and install 2 new light fixtures per plan. 2 new lights total.
Reinstall 8 existing lights to accommodate several new office areas. 8 lights reworked total.
2.0 SPECIFICATIONS:
As provided by City of Anna Personnel and are described in the scope of work.
2.1 DRAWING AND SKETCHES:
Sketches and drawings not provided.
2.2 SPECIFICATIONS:
Work shall be performed per the latest edition of the applicable federal, state, and local codes and standards.
Scope of Work Page 5 of 6
8/6/2025
Detailed Scope of Work Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
3.0 SUBMITTALS:
Structured shall submit the indicated number of copies of each required submittal. Submittals shall be
submitted and approved prior to incorporating that material or activity into the project. Submittals required by
specification and/or drawings shall be made regardless of whether or not they are listed on this schedule.
4.0 SPECIAL CONSIDERATIONS:
Special considerations are applicable to this project as outlined in the following:
4.1 Structured will contact the customer project manager to coordinate scheduled equipment outages if
required.
4.2 Normal working hours for this project are Monday through Friday 8:00 am — 5:00 pm. Working
outside of normal working hours or on holidays will be coordinated and approved by the customer. The scope
of work does not include the cost of work outside of normal working hours unless noted.
4.3 All work performed shall be in accordance with the applicable requirements of the latest edition of the
Occupational Safety and Health Act (OSHA), Structured safety requirements and customer procedures as
provided to Structured.
4.4 This proposal is valid for 28 days.
5.0 Exclusions:
The following items are excluded from the scope of work:
Asbestos or lead abatement
S WPPP
Anything not specified in
Subject to the terms and conditions of JOC Contract TX-R3-GC-052124-SCL.
Contractor
Owner
Scope of Work
Date
Date
Page 6 of 6
8/6/2025
8/13/2025
Contractor's Price Proposal - Summary
Date: August 06, 2025
Re: IQC Master Contract #:
Work Order*
Owner PO #:
Title:
Contractor:
Proposal Value:
TX-R3-GC-052124-SCL
146114.00
Anna - Public Works Building Reno
Structured Construction LLC
164,238.33
Division 01 (Safety/General Requirements) 5,477.97
Division 02 (Existing Conditions) 19,169.34
Division 05 (Metals) 2,051.31
Division 08 (Openings) 11,397.27
Division 09 (Finishes) 107,902.27
Division 12 (Furnishings) 1,627.44
Division 22 (Plumbing) 6,606.96
Division 26 (Electrical) 10,005.77
Proposal Total 164,238.33
Thisl total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
Contractor's Price Proposal - Summary Page 1 of 1
8/6/2025
Contractor's Price Proposal - Detail
Date: August 06, 2025
Re: IQC Master Contract #: TX-R3-GC-052124-SCL
Work Order #: 146114.00
Owner PO #:
Title: Anna - Public Works Building Reno
Contractor: Structured Construction LLC
Proposal Value: 164,238.33
Sect. Item Mod. UOM Description Line Total
Labor Equip. Material (Excludes)
Division 01 (Safety/General Requirements)
1 01 56 16 00 0010 SF 6 Mil, Plastic Sheeting, Applied To Ceilingslncludes removal after use. 1,593.24
Quantity Unit Price Factor Total
Installation
4,152.30 x 0.30
x 1.2790 1,593.24
Provide and install approximately 4152.3 square feet of 6 mil plastic to protect all of the ceilings. 4152.3
square feet total.
2 oll 74 19 00 0015 EA 30 CY Dumpster (4 Ton) "Construction Debris"Includes delivery of dumpster, 3,884.73
rental cost, pick-up cost, hauling, and disposal fee. Non -hazardous material.
Quantity Unit Price Factor Total
Installation
4.00 x 759.33
x 1.2790 3,884.73
Provide 4 - 30 yard dumpsters for debris removal from site. 4 dumpsters total.
Subtotal for Division 01 (Safety/General Requirements) 5,477.97
Division 02 (Existing Conditions)
3 02 41 16 13 0027 CIF Reinforced Concrete Foundation Demolition 333.05
Quantity Unit Price Factor Total
Installation
30.00 x 8.68 x 1.2790
333.05
Demo and remove approximately 30 cubit feet of existing slab to open up the slab to run new plumbing in the
small breakroom. 30 cubit feet total.
4 02 41 19 13 0058 EA Saw Cut Minimum ChargeFor projects where the total saw cutting charge is 955.36
less than the minimum charge, use this task exclusively. This task should not
be used in conjunction with any other tasks in this section.
Quantity Unit Price Factor Total
Installation
1.00 x 746.96 x 1.2790 955.36
Sawcut approximately 55 linear feet of existing concrete slab to install new plumbing in the small breakroom.
55 linear feet total.
5 06 41 13 00 0002 LF Removal And Reinstallation Of Wood Base Cabinets 1.000.54
Quantity Unit Price Factor Total
Installation
1800 x 43.46 x 1.2790 1,000.54
Remove and reinstall base cabinets in big break room into small break room. 18 linear feet total.
6 06 41 13 00 0003 LF Removal And Reinstallation Of Wall Cabinets 870.00
Quantity Unit Price Factor Total
Installation
18.00 x 37.79 x 1.2790
870.00
Remove and reinstall upper cabinets in big break room into small break room. 18 linear feet total.
7 06 41 13 00 0004 LF Removal And Reinstallation Of Plastic Laminated Countertops 218.94
Quantity Unit Price Factor Total
Installation
18.00 x 9.51 x 1.2790 218.94
Remove and reinstall countertops in big break room into small break room. 18 linear feet total.
8 06 41 13 00 0016 EA 36" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid 130.77
Maple Face Frame, Door and Drawer Front, Base Cabinet
Quantity Unit Price Factor Total
Installation
0.00 x 580.06 x 1.2790 0.00
Demolition 3.00 x 34.08 x 1,2790 = 130.76
Demo and remove 3 - 36" wide base cabinets in small breakroom. 3 base cabinets total.
Contractor's Price Proposal - Detail Page 1 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 02 (Existina Conditions)
9 06 41 13 00 0017 EA 48" Wide, 35" High x 23-3/4" Deep, Double Drawer and Double Door, Solid 58.13
Maple Face Frame, Door and Drawer Front, Base Cabinet
Quantity Unit Price Factor Total
Installation
0.00 x 664.62 x 1.2790 0.00
Demolition 1,00 x 45.45 x 1.2790 = 58.13
Demo and remove 1 - 48" wide base cabinet in small breakroom. 1 base cabinet total.
10 06 41 13 00 0076 EA 12" Wide, 36" High x 12" Deep, Single Door, Solid Maple Face Frame and 14.53
Door, Wall Cabinet
Quantity Unit Price Factor Total
Installation
0.00 x 329.02 x 1.2790
0.00
Demolition 1.00 x 11.36 x 1.2790 = 14.53
Demo and remove 1 - 12" wide wall cabinet in small breakroom. 1 wall cabinet total.
11 06 41 13 00 0084 EA 36" Wide. 36" High x 12" Deep, Double Door, Solid Maple Face Frame and 174.35
Door, Wall Cabinet
Quantity Unit Price Factor Total
Installation
0 0o x 579.81 x 1.2790 = 0.00
Demolition 4.00 x 34.08 x 1.2790 = 174.35
Demo and remove 4 - 36" wide wall cabinets in small breakroom. 4 wall cabinets total.
12 08 12 13 13 0008 EA Tx 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow 145.29
Metal Door Frame
Quantity Unit Price Factor Total
Installation
0.00 x 823.35 x 1.2790 0.00
Demolition 2.00 x 56.80 x 1.2790 = 145.29
Demo 2 existing door frames per plan. Salvage 1 HM frame only, dispose of the other wood frame. 2 total.
13 08 14 16 00 0354 EA 3'-0" x 7' x 1-3/8" Thick, 5 Ply, Particleboard Core (PC), Oak Faced Wood Door 43.59
Quantity Unit Price Factor Total
Installation
0.00 x 432,48 x 1.2790 0.00
Demolition 1.00 x 34.08 x 1.2790 = 43.59
Demo and salvage of 1 existing solid core door. 1 total.
14 08 51 13 00 0075 EA Up To 6 SF, 3-1/4" Frame Depth, HC 60, One Rolling Sash And One Stationary 69.74
Sash, Horizontal Sliding Aluminum Window (Traco TR-6800)
Quantity Unit Price Factor Total
Installation
0.00 x 2,059.97 x 1.2790 0.00
Demolition 1.00 x 54.53 x 1.2790 = 69.74
Demo and remove existing glass window. Approximately 4 square feet window 24" x 24".
15 08 71 11 00 2288 EA Heavy -Duty Cylindrical, F86 Storeroom Or Closet LocksetSatin chrome plated 18.16
US26D (BHMA 626) - BHMA 156.2-1989, Grade 1(Corbin Russwin CL 3600).
Quantity Unit Price Factor Total
Installation
0.00 x 641.41 x 1.2790 0.00
Demolition 1.00 x 14.20 x 1.2790 = 18.16
Remove 1 lockset/door knob and salvage to reinstall on salvaged door. 1 total.
16 09 30 13 00 0004 SF 8" x 8" And Larger Unmounted Ceramic Floor Tilelncludes glazed porcelain, 173.24
unglazed porcelain and glazed ceramic tiles.
Quantity Unit Price Factor Total
Installation
0.00 x 10.06 x 1.2790 0.00
Demolition 129.00 x 1.05 x 1.2790 = 173.24
Demo and dispose of approximately 129 square feet of ceramic the flooring in the entry way. 129 square feet
total.
17 09 31 13 00 0002 SF Thin Set - Latex Portland Cement Mortar 92.40
Quantity Unit Price Factor Total
Installation
0.00 x 1.10 x 1.2790 0.00
Demolition 129.00 x 0.56 x 1.2790 = 92.39
Demo and dispose of approximately 129 square feet of thin set for the old ceramic tile in the front entry. 129
square feet total.
Contractor's Price Proposal - Detail Page 2 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 02 (Existina Conditions)
18 09 65 13 13 0010 LF 4" High, 1/8" Thick, Type TP Thermoplastic Rubber Wall Base, All Colors 1,493.26
Quantity Unit Price Factor Total
Installation
0.00 x 4.96 x 1.2790 0•Go
Demolition 1,644.40 x 0.71 x 1.2790 = 1,493.26
Demo and dispose of approximately 1644.4 linear feet of resilient baseboard. 1644.4 linear feet total.
19 09 65 19 19 0011 SF 1/8" Thick, Class 1 Solid Color, Vinyl Composition Tile (VCT) (Armstrong® 3,230.47
Excelon FeatureTm)
Quantity Unit Price Factor Total
Installation
0.00 x 10.62 x 1.2790 0.00
Demolition 2,971.50 x 0.85 x 1.2790 = 3,230.47
Demo and remove approximately 2971.5 square feet of VCT per plan. 2971.5 square feet total.
20 09 67 23 00 0004 SF 3/16" Heavy -Duty (6,000 To 7,500 PSI) Epoxy Flooring Trowel Applied Mortar 1,097.38
Compound Includes primer, one 3/16" slurry coat and top seal coats (color).
Quantity Unit Price Factor Total
Installation
0.00 x 9.73 x 1.2790 0.00
Demolition 264,00 x 3.25 x 1.2790 = 1,097.38
Demo and remove approximately 264 square feet of existing epoxy flooring. 264 square feet total.
21 09 68 16 00 0057 SY 34 Ounce, Medium Traffic, Non -Patterned, Nylon Broadloom Carpet 6,708.46
Quantity Unit Price Factor Total
Installation
0.00 x 57.50 x 1.2790 0.00
Demolition 320.80 x 16.35 x 1.2790 = 6,708.46
Demo and remove approximately 320.8 square yards of existing carpet. 320.8 square yards total.
22 12 36 23 13 0003 SF Plastic Laminate Countertop With 4" Backsplash 87.02
Quantity Unit Price Factor Total
Installation =
0.00 x 15.06 x 1.2790 0.00
Demolition 12.00 x 5.67 x 1.2790 = 87.02
Demo and remove existing countertop in men's locker room. Approximately 12 square feet total.
23 12 36 23 13 0003 SF Plastic Laminate Countertop With 4" Backsplash 65.27
Quantity Unit Price Factor Total
Installation
0.00 x 15.06 x 1.2790 0.00
Demolition 9.00 x 5.67 x 1.2790 = 65.27
Demo and remove approximately 9 square feet of existing countertops in small break room area. 9 square feet
total.
24 12 36 61 16 0005 SF 314" Thick, Solid Color, Solid Surface Countertop Without BacksplashQuantity 174.05
based on area of counter, backsplash and apron. Includes drilling holes for
fixtures and 1-1/2" drop edge with 1/8" radius edges (when apron not used).
Quantity Unit Price Factor Total
Installation
0.00 x 72.04 x 1.2790 = 0.00
Demolition 24.00 x 5.67 x 1.2790 = 174.05
Demo and remove approximately 24 square feet of countertop per plan in front lobby. 24 square feet total.
25 22 11 16 00 0388 LF 1/2" Hard Drawn Type L Copper Tube/Pipe 40.93
Quantity Unit Price Factor Total
Installation
0.00 x 5.09 x 1.2790
0.00
Demolition 20.00 x 1.60 x 1.2790 = 40.93
Demo and remove 20 linear feet of existing copper tubing per plan in small break room. 20 linear feet total.
26 22 11 16 00 0455 EA 1/2" 90 Degree Copper Elbow 73.93
Quantity Unit Price Factor Total
Installation
0.00 x 22.75 x 1,2790
0.00
Demolition 4.00 x 14.45 x 1.2790 = 73.93
Demo and remove approximately 4 - 1/2" 90's per plan. 4 - 90's total.
Contractor's Price Proposal - Detail Page 3 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 02 (Existinq Conditions)
27 22 11 16 00 0500 EA 1/2" Straight Copper Tee 56.10
Quantity Unit Price Factor Total
Installation
0.00 x 34.70 x 1.2790 0.00
Demolition 2.00 x 21.93 x 1.2790 = 56.10
Demo and remove approximately 2 - 1/2" copper tees in small breakroom area. 2 total.
28 22 11 16 00 0527 EA 1/2" Copper Coupling 61.14
Quantity Unit Price Factor Total
Installation
0.00 x 18.68 x 1.2790 0.00
Demolition 4.00 x 11.95 x 1.2790 = 61.14
Demo and remove 4 - 1/2" copper couplings in small breakroom. 4 couplings total.
29 22 13 16 00 0525 LF 2" Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe 77.51
Quantity Unit Price Factor Total
Installation
0.00 x 8.50
x 1.2790 0.00
Demolition 20,00 x 3.03 x 1.2790 = 77.51
Demo and remove approximately 20 linear feet of pvc pipe in small breakroom area. 20 linear feet total.
30 22 13 16 00 0542 EA 2" Polyvinyl Chloride (PVC) DWV 1/4 Bends 33.00
Quantity Unit Price Factor Total
Installation
0.00 x 30.38 x 1.2790 0.00
Demolition 2.00 x 12.90 x 1.2790 = 33.00
Demo and remove 2 - 2" pvc 90's in small breakroom. 2- 90's total.
31 22 13 16 00 0566 EA 2" Polyvinyl Chloride (PVC) DWV Sanitary Tees 24.77
Quantity Unit Price Factor Total
Installation
0.00 x 51.24 x 1.2790 0,00
Demolition 1.00 x 19.37 x 1.2790 = 24.77
Demo and remove 1 - 2" pvc sanitary tee in small breakroom. 1 tee total.
32 22 13 16 00 0608 EA 2" Polyvinyl Chloride (PVC) DWV P-Traps 49.55
Quantity Unit Price Factor Total
Installation
0.00 x 70.42 x 1.2790
0.00
Demolition 2.00 x 19.37 x 1.2790 = 49.55
Demo and remove 2 existing p-traps from men's locker room and small break room.
33 22 13 16 00 0617 EA 2" Polyvinyl Chloride (PVC) DWV Wyes 49.55
Quantity Unit Price Factor Total
Installation
0.00 x 60.25 x 1.2790 0.00
Demolition 2.00 x 19,37 x 1.2790 = 49.55
Demo and remove 2 - 2" wye's in small breakroom. 2 wye's total.
34 22 13 16 00 0682 EA 2" Polyvinyl Chloride (PVC) DWV Cleanout Tees With Plug 24.77
Quantity Unit Price Factor Total
Installation
0.00 x 176.70 x 1.2790 0.00
Demolition 1.00 x 19.37 x 1.2790 = 24.77
Demo and remove 1 - 2" cleanout tee in small breakroom. 1 cleanout tee total.
35 22 42 39 00 0025 EA Single Handle Centerset Lavatory Faucet, Polished Chrome Finish (Delta 55.74
Lahara 538-MPU-DST)
Quantity Unit Price Factor Total
Installation
0.00 x 249.68 x 1.2790 0.00
Demolition 2.00 x 21.79 x 1.2790 = 55.74
Demo and remove 2 sinks in men's locker room. 2 sinks total.
36 22 42 39 00 0176 EA 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Angle Stop (SharkBite 16.24
23036)
Quantity Unit Price Factor Total
Installation
0.00 x 30.27 x 1.2790 0.00
Demolition 2.00 x 6.35 x 1.2790 = 16.24
Demo and remove 2 - 1/2" angle valves in small breakroom. 2 angle valves total.
Contractor's Price Proposal - Detail Page 4 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 02 (Existina Conditions)
37 22 43 16 00 0004 EA 28" x 22", Wall Mounted, Vitreous China Surgeon's Scrub Sink (American 103.73
Standard)
Quantity Unit Price Factor Total
Installation
0.00 x 1,011.49 x 1.2790
0,00
Demolition 2.00 x 40.55 x 1.2790 = 103.73
Demo and Remove existing 2 sinks in mens locker room. 2 sinks removed total.
38 26 05 19 16 0205 MLF 4 Conductors, #12 AWG, Type MC, Solid Or Stranded, Galvanized Steel 641.50
Armored Cable
Quantity Unit Price Factor Total
Installation
0.00 x 3,950.43 x 1.2790
0.00
Demolition 0.60 x 835.94 x 1.2790 = 641.50
Demo and remove approximately 600 linear feet or armored cable per plan. 600 linear feet total.
39 26 05 19 16 0246 EA 3/4" Armored Cable Connector 49.88
Quantity Unit Price Factor Total
Installation
0.00 x 4.03 x 1.2790 0.00
Demolition 30.00 x 1.30 x 1.2790 = 49.88
Demo and dispose of approximately 30 connectors. 30 connectors total.
40 26 05 33 13 0014 CLF 3/4" Electrical Metallic Tubing (EMT) Conduit Assembly With 2 #10 Copper 227.89
THHN And 1 #12 Copper Insulated Grounding Conductorincludes conduit, set
screw connectors, set screw couplings, straps, wire as indicated. Not for use
where detail is available.
Quantity Unit Price Factor Total
Installation
0.00 x 622.20 x 1.2790 =
0.00
Demolition 1.20 x 148.48 x 1.2790 = 227.89
Demo and remove approximately 120 linear feet of existing 3/4" EMT per plan. 120 linear feet total.
41 26 05 33 16 0005 EA 3-1/2" Depth, 4" Square Steel Box 170.75
Quantity Unit Price Factor Total
Installation
0.00 x 24.99 x 1.2790 0.00
Demolition 15.00 x 8.90 x 1.2790 = 170.75
Demo and remove approximately 15 electrical boxes per plan in offices, small breakroom area, and the large
breakroom area. 15 steel boxes total.
42 26 51 19 00 0039 EA 2' x 4', 4,600 Lumens, Prismatic Lensed, Lay-In/Troffer LED Fixture (Lithonia 258.36
2TL4)
Quantity Unit Price Factor Total
Installation =
0.00 x 575.04 x 1.2790
0.00
Demolition 8.00 x 25.25 x 1.2790 = 258.36
Remove and salvage approximately 8 existing light fixtures. 8 lights total.
Subtotal for Division 02 (Existing Conditions) 19,169.34
Division 05 (Metals)
43 01 22 20 00 0038 HR WelderFor tasks not included in the Construction Task Catalog® and as 1,485.99
directed by owner only.
Quantity Unit Price Factor Total
Installation
24.00 x 48.41 x 1.2790 1,485.99
Provide welder to fabricate metal frame to be hung on the wall in men's locker room for new big sink. includes
installation of frame. This includes time for shop drawings/design, shop fabrication and onsite installation
onsite. 24 hours total.
44 05 12 23 00 0695 LF 2" x 2" x 1/8" Square Steel Tubing 565.32
Quantity Unit Price Factor Total
Installation
40.00 x 11.05 x 1.2790
565.32
Provide and install approximately 40 linear feet of square tubing to be fabricated into a frame for the new
men's locker room sink. 40 linear feet total.
Subtotal for Division 05 (Metals) 2,051.31
Contractor's Price Proposal - Detail Page 5 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 08 (Openings)
45 08 12 13 13 0008 EA Tx 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow 3,159.19
Metal Door Frame
Quantity Unit Price Factor Total
Installation
3.00
x 823.35 x 1.2790 3.159.19
Provide and install three 3' x 7' HIM door frames per plan. 3 total.
46 08 12 13 13 0008 0069 For Auxiliary Frame Reinforcement For Hinges, Add 408.49
Quantity Unit Price Factor Total
Installation
3.00 x 106.46
x 1.2790 408.49
47 08 14 16 00 0354 EA 3'-0" x Tx 1-3/8" Thick, 5 Ply, Particleboard Core (PC), Oak Faced Wood Door 1,659.43
Quantity Unit Price Factor Total
Installation
3.00 x 432.48 x 12790 1,659.43
Provide and install 3 doors per plan. 3 doors total.
48 08 51 13 00 0076 EA >6 To 10 SF, 3-1/4" Frame Depth, HC 60, One Rolling Sash And One 3,000.48
Stationary Sash, Horizontal Sliding Aluminum Window (Traco TR-6800)
Quantity Unit Price Factor Total
Installation
100 x 2,345.96 x 1.2790 3,000.48
Provide and install 1 new 36" x 36" aluminum sliding glass window at lobby per plan. 1 sliding glass window
total.
49 08 51 13 00 0076 0071 For Clear Anodized Finish, Add 143.85
Quantity Unit Price Factor Total
Installation =
1.00 x 112.47 x 1.2790 143.85
50 08 71 11 00 0027 PR 4-1/2" x 4-1/2" Heavy -Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin 446.05
Chrome Finish Hinge
Quantity Unit Price Factor Total
Installation
3.00
x 116.25 x 12790 446.05
Provide and install 2 sets (3 per set) of hinges per plan. 1.5 hinges x 2 doors = 3 hinge pairs total.
51 08 71 11 00 0027 0202 MOD For Pair Of Non -Removable Pins (NRP), Add 46.04
Quantity Unit Price Factor Total
Installation
6.00 x 6.00
x 1.2790 46.04
52 08 71 11 00 2288 EA Heavy -Duty Cylindrical, F86 Storeroom Or Closet LocksetSatin chrome plated 2,461.09
US26D (BHMA 626) - BHMA 156.2-1989, Grade 1(Corbin Russwin CL 3600).
Quantity Unit Price Factor Total
Installation
3.00 x 641.41 x 1.2790 2,461.09
Provide and install 3 lockets per plan. 3 locksets total.
53 08 71 11 00 2288 EA Heavy -Duty Cylindrical, F86 Storeroom Or Closet LocksetSatin chrome plated 72.65
US26D (BHMA 626) - BHMA 156.2-1989, Grade 1(Corbin Russwin CL 3600).
Quantity Unit Price Factor Total
X Installation
100 x 56.80 x 1.2790 72.65
Reinstall 1 salvaged lockset/door knob. 1 lockset total.
Subtotal for Division 08 (Openings) 11,397.27
Division 09 (Finishes)
54 01 45 23 00 0093 EA First Unit, Moisture Condition By Relative Humidity, ASTM C427 612.99
Quantity Unit Price Factor Total
Installation
100 x 479.27 x 1.2790 612.99
Perform first moisture test for new LVT flooring required for flooring warranty. 1 primary test total.
55 D1 45 23 00 0094 EA Moisture Condition By Relative Humidity, ASTM C427, Additional Unit 1,838.92
Quantity Unit Price Factor Total
Installation =
6.00 x 239.63 x 1.2790 1,838.92
Perform 6 moisture tests for new LVT flooring required for flooring warranty. One secondary test is required per
1,000 square feet. 6 secondary tests total.
Contractor's Price Proposal - Detail Page 6 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 09 (Finishes)
56 02 41 19 16 0046 SF Demolish Wood Or Metal Framed Interior Partition/Wall With Drywall 2 Sides $183.80
Quantity Unit Price Factor Total
Installation
10120 x 1.42 x 1.2790 183.80
Demo and remove approximately 101.2 square feet of walls per plan. 101.2 square feet total.
57 03 54 16 00 0002 SF 1/8" Thick Self Leveling Cementitious Undedayment For Floorslncluding 6,678.76
Surface Preparation
Quantity Unit Price Factor Total
Installation
3,145.70 x 1.66 x 1,2790 - 6,678.76
Provide and install approximately 3145.7 square feet of a W self leveling underlayment for new LVT flooring.
50°f coverage. 3145.7 square feet total.
58 09 01 20 91 0002 SF Up To 2 SF, Cut And Patch Hole In Gypsum Board To Match ExisfingPer 7,267.69
location.
Quantity Unit Price Factor Total
Installation
511.00 x 11.12 x 1.2790 7,267.69
Patch approximately 511 square feet of wall in various locations to prep for paint. 511 square feet total.
59 09 22 16 13 0010 SF 3-5/8" Width, 16" On Center, 20 Gauge, Non -Load Bearing, Non -Structural, 2,516.55
Galvanized Steel Stud Framing With Tracks And Runners
Quantity Unit Price Factor Total
Installation
616.80 x 3.19 x 1.2790 2,516.55
Provide and install approximately 616.8 square feet of new metal stud walls per plan. 618,8 square feet total.
60 09 22 16 13 0010 0001 MOD For Powder -Actuated Fasteners Every 2', Add 31.56
Quantity Unit Price Factor Total
Installation
616.80 x 0.04 x 1,2790 31.56
61 09 29 10 00 0009 SF 5/8" Type X Fire Rated Gypsum Board 2,098.44
Quantity Unit Price Factor Total
Installation =
1,233.60 x 1.33 x 1.2790 2,098.44
Provide and install approximately 1233.6 square feet Type X gypsum board per plan. 1233.6 square feet total.
62 09 29 10 00 0038 SF Up To 10' High, Walls, Tape, Spackle And Finish Gypsum Board 536.44
Quantity Unit Price Factor Total
Installation
1,233.60 x 0.34 x 1.2790 - 536.44
Provide and install approximately 1233.6 square feet tape, spackle and wall finish per plan. 1233.6 square feet
total. No texture will be applied to new walls, smooth finish only.
63 09 51 13 00 0003 SF 2' x 2' x 3/4" Thick, Square Edge, Fiberglass Acoustical Ceiling Panel 314.25
Armstrong Optima(&)
Quantity Unit Price Factor Total
Installation
30.00 x 8.19 x 1.2790 314.25
Rework existing ceilings tiles to accommodate new wall that goes above ceiling in the lobby. Approximately 30
square feet total.
64 09 51 13 00 0003 0093 For Up To 50, Add 58.32
Quantity Unit Price Factor Total
Installation
30.00 x 1.52 x 1.2790 58.32
65 09 53 23 00 0004 SF 2' x 2' Grid, Hot Dipped Galvanized Steel, 15/16" T Bar Ceiling Suspension 89.79
System
Quantity Unit Price Factor Total
Installation
30.00 x 2.34 x 1.2790 89.79
Rework ceiling grid in lobby at new wall that goes above ceiling. Approximately 30 square feet total.
66 09 53 23 00 0004 0120 For Up To 50, Add 28.01
Quantity Unit Price Factor Total
Installation
30.00 x 0.73 x 1.2790 28.01
Contractor's Price Proposal - Detail Page 7 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order (dumber: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 09 (Finishes)
67 09 65 13 13 0010 LF 4" High, 1/8" Thick, Type TP Thermoplastic Rubber Wall Base, All Colors $10,431.81
Quantity Unit Price Factor Total
Installation
164440 x 4.96 x 1.2790 10,431.81
Provide and install approximately 1644.4 linear feet of new rubber baseboards throughout entire space. 1644.4
linear feet total.
68 09 65 13 130010 0447 For >960, Deduct 1,346.04
Quantity Unit Price Factor Total
Installation
1,644.40 x -0.64 x 1.2790 - 1,346.04
69 09 65 13 36 0007 LF 1/4" To 1/8" Material x 1-3/4", Vinyl, Wheeled Traffic Transition (Johnsonite 84.63
CTA-XX-A)
Quantity Unit Price Factor Total
Installation
0.00 x 3.19 x 1.2790 0.00
Demolition 93.20 x 0.71 x 1.2790 = 84.63
Demo and remove approximately 93.2 linear feet of transition striping per plan. 93.2 linear feet total.
70 09 65 23 00 0004 SF 0.16" Overall Thickness, 0.020" Wear Layer, Vinyl Plank Flooring (Armstrong(D 72,982.41
Luxe PlankTM')
Quantity Unit Price Factor Total
Installation
6,291.30 x 9.07 x 1.2790 72,982.41
Provide and install approximately 6291.3 square feet of new LVT flooring throughout the entire space. 6291.3
square feet of flooring total.
71 09 65 23 00 0004 0138 For>1,000, Deduct 6,598.19
Quantity Unit Price Factor Total
Installation
6,291.30 x -0.82 x 1.2790 6,598.19
72 09 91 23 00 0066 SF 1 Coat Primer, Brush/Roller Work, Paint Interior Plaster/Drywall Walls 3,569.31
Quantity Unit Price Factor Total
Installation
6,490.00 x 0.43 x 1.2790 3,569.31
Provide and install 1 coat of primer for approximately 6490 square feet on all walls inside new space per plan.
6490 square feet total.
73 09 91 23 00 0066 0283 For >5,000 To 10,000, Deduct 332.03
Quantity Unit Price Factor Total
Installation
6,490.00 x -0.04 x 1.2790
332.03
74 09 91 23 00 0068 SF 2 Coats Paint, Brush/Roller Work, Paint Interior Plaster/Drywall Walls 7,055.60
Quantity Unit Price Factor Total
Installation
6,490.00 x 0.85 x 1.2790 - 7,055.60
Provide and install 2 coats of paint for approximately 6490 square feet on all walls inside new space per plan.
6490 square feet total.
75 09 91 23 DO 0068 0283 For >5,000 To 10,000, Deduct 747.06
Quantity Unit Price Factor Total
Installation
6.490.00 x -0.09 x 1.2790 747.06
76 09 91 23 00 0250 LF 1 Coat Primer, Brush/Roller Work, Paint Interior Metal Door Frame And Trim 28,27
Quantity Unit Price Factor Total
Installation
34.00 x 0.65 x 1.2790 28.27
Provide and install 1 coat primer for 2 new HIM door frames per plan. 34 linear feet total.
77 09 91 23 00 0250 0289 For Oil Based Paint, Add 1.74
Quantity Unit Price Factor Total
Installation
34.00 x 0.04 x 1.2790
1.74
78 09 91 23 00 0252 LF 2 Coats Paint, Brush/Roller Work, Paint Interior Metal Door Frame And Trim 58.27
Quantity Unit Price Factor Total
Installation
34.00 x 1.34 x 1.2790 - 58.27
Provide and install 2 coats paint for 2 new HIM door frames per plan. 34 linear feet total.
Contractor's Price Proposal - Detail Page 8 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 09 (Finishes)
79 09 91 23 00 0252 0289 For Oil Based Paint, Add 3.48
Quantity Unit Price Factor Total
Installation
34.00 x 0.08 x 1.2790
3.48
80 09 91 23 00 0270 EA 1 Coat Primer, Brush/Roller Work, Both Faces, Paint Interior Wood Door 148.13
Quantity Unit Price Factor Total
Installation
2.00 x 57.91 x 1.2790 148.13
Provide and install 1 coat primer for 2 new wood doors per plan. 2 doors total.
81 09 91 23 00 0270 0289 For Oil Based Paint, Add 11,20
Quantity Unit Price Factor Total
Installation
2.00 x 4.38
x 1.2790 11.20
82 09 91 23 00 0272 EA 2 Coats Paint, Brush/Roller Work, Both Faces, Paint Interior Wood Door 273.96
Quantity Unit Price Factor Total
Installation
2.00 x 107.10 x 1.2790 273.96
Provide and install 2 coats paint for 2 new wood doors per plan. 2 doors total.
83 09 91 23 00 0272 0289 For Oil Based Paint, Add 21.26
Quantity Unit Price Factor Total
Installation =
2.00 x 8.31 x 1.2790 21.26
Subtotal for Division 09 (Finishes) 107,902.27
Division 12 Furnishings)
84 12 36 61 16 0006 SF 1/2" Thick, Solid Color, Solid Surface Countertop With 4" Backsplash 916.74
Quantity Unit Price Factor Total
Installation
12.00 x 59.73 x 1.2790 916.74
Provide and install new men's locker room sink solid surface countertop. Approximately 12 square feet total.
85 12 36 61 16 0006 0021 For Up To 50, Add 303.43
Quantity Unit Price Factor Total
Installation
12.00 x 19.77 x 1.2790 303.43
86 12 36 61 16 0007 LF 1/2" Thick, Solid Color, Solid Surface 4" End Splash For Solid Surface 298.39
Countertops
Quantity Unit Price Factor Total
Installation
10.00 x 23.33 x 1.2790
298.39
Provide and install new men's locker room sink solid surface countertop end splash guard Approximately 1
linear feet total.
87 12 36 61 16 0008 EA Cutout For Undercounter Sink In Solid Surface CountertopNot including 108.88
integral seamed sinks
Quantity Unit Price Factor Total
Installation
1.00 x 85.13 x 1.2790
108.88
Provide and install one cutout for big sink in men's locker room new solid surface countertop. 1 cutout total.
Subtotal for Division 12 (Furnishings) 1,627.44
Division 22 (Plumbing)
88 01 22 20 00 0024 HR PlumberFor tasks not included in the Construction Task Catalog(R) and as 1,315.63
directed by owner only.
Quantity Unit Price Factor Total
Installation
16.00 x 64.29 x 1.2790
1,315.63
Hours for plumber to rework plumbing (drains and waterlines) underneath new big sink in men's locker room.
16 hours total.
Contractor's Price Proposal - Detail Page 9 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 22 (Plumbing)
89 22 11 16 00 0388 LF 1/2" Hard Drawn Type L Copper Tube/Pipe $390.61
Quantity Unit Price Factor Total
Installation
60.00 x
5.09
x 1.2790 390.61
Provide and install 60 linear feet of 1/2" copper pipe for small breakroom plumbing relocation. 60 linear feet
total.
90 22 11 16 00 0388 0259 MOD For Work In Restricted Working Space, Add 55.25
Quantity Unit Price Factor Total
Installation
60.00 x 0.72 x 1.2790
55.25
91 22 11 16 00 0455 EA 1/2" 90 Degree Copper Elbow 349.17
Quantity Unit Price Factor Total
Installation
12.00
x 22.75 x 1.2790 =
349.17
Provide and install twelve 1/2" copper 90's for small breakroom plumbing relocation. 12 - 90's total.
92 22 11 16 00 0455 0259 MOD For Work In Restricted Working Space, Add 99.76
Quantity Unit Price Factor Total
Installation
12.00 x 6.50
x 1.2790 99.76
93 22 11 16 00 0500 EA 112" Straight Copper Tee 88.76
Quantity Unit Price Factor Total
Installation
2.00 x 34.70 x 1.2790 88.76
Provide and install two 1/2" copper tees for small breakroom plumbing relocation. 2 tees total.
94 22 11 16 00 0500 0259 MOD For Work In Restricted Working Space, Add 25.22
Quantity Unit Price Factor Total
Installation
2.00 x 9.86
x 1.2790 25.22
95 22 11 16 00 0527 EA 1/2" Copper Coupling 95.57
Quantity Unit Price Factor Total
Installation
4.00 x 18.68 x 1.2790 -
95.57
Provide and install four 1/2" copper couplings for small breakroom plumbing relocation. 4 couplings total.
96 22 11 16 00 0527 0259 MOD For Work In Restricted Working Space, Add 27.63
Quantity Unit Price Factor Total
Installation
4.00 x 5.40 x 1.2790
27.63
97 22 11 16 00 0621 EA 1/2" Copper Cap 40.62
Quantity Unit Price Factor Total
Installation
4.00 x 7.94 x 1.2790 40.62
Provide and install four 1/2" copper caps for small breakroom plumbing relocation. 4 caps total.
98 22 11 16 00 0621 0259 MOD For Work In Restricted Working Space, Add 11.00
Quantity Unit Price Factor Total
Installation
4.00 x 2.15
x 1.2790 11.00
99 22 13 16 00 0525 LF 2" Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe 652.29
Quantity Unit Price Factor Total
Installation
60.00 x 8.50
x 1.2790 = 652.29
Provide and install approximately 60 linear feet of 2" DWV PVC pipe for small breakroom relocation of
plumbing. 60 linear feet total.
100 22 13 16 00 0525 0198 MOD For Work In Restricted Working Space, Add 104.37
Quantity Unit Price Factor Total
Installation
60.00 x 1.36 x 1.2790 = 104.37
101 22 13 16 00 0542 EA 2" Polyvinyl Chloride (PVC) DWV 1/4 Bends 155.42
Quantity Unit Price Factor Total
Installation
4.00 x 30.38
x 1.2790 = 155.42
Provide and install 4 - 90's for small breakroom relocation of plumbing. 4 - 90's total.
Contractor's Price Proposal - Detail Page 10 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 22 (Plumbing)
102 22 13 16 00 0542 0198 MOD For Work In Restricted Working Space, Add 29.72
Quantity Unit Price Factor Total
Installation
4.00 x 5.81 x 1.2790 29.72
103 22 13 16 00 0566 EA 2" Polyvinyl Chloride (PVC) DWV Sanitary Tees 65.54
Quantity Unit Price Factor Total
Installation
1.00 x 51.24 x 1.2790 65.54
Provide and install 1 sanitary tee for small breakroom relocation of plumbing. 1 sanitary tee total.
104 22 13 16 00 0566 0198 MOD For Work In Restricted Working Space, Add 11.15
Quantity Unit Price Factor Total
Installation =
1.00 x 8.72 x 1.2790 11.15
105 22 13 16 00 0640 EA 2" Polyvinyl Chloride (PVC) DWV Double Wyes 316.25
Quantity Unit Price Factor Total
Installation
2.00 x 123.63 x 1.2790 = 316.25
Provide and install 2 wyes for small breakroom relocation of plumbing. 2 wyes total.
106 22 13 16 00 0640 0198 MOD For Work In Restricted Working Space, Add 29.72
Quantity Unit Price Factor Total
Installation
2.00 x 11,62 x 1.2790 29.72
107 22 13 16 00 0682 EA 2" Polyvinyl Chloride (PVC) DWV Cleanout Tees With Plug 226.00
Quantity Unit Price Factor Total
Installation
1.00 x 176.70 x 1.2790 = 226.00
Provide and install 1 test tee with plug for small breakroom relocation of plumbing. 1 test tee total.
108 22 13 16 00 0682 0198 MOD For Work In Restricted Working Space, Add 11.15
Quantity Unit Price Factor Total
Installation
1.00 x 8.72 x 1.2790 = 11.15
109 22 42 16 16 0056 EA 36" x 18-1/2" x 10" Double Bowl Soapstone Sink 1,790.02
Quantity Unit Price Factor Total
Installation
1.00 x 1,399.55 x 1.2790 1,790.02
Provide and install one undermount 40" to 48" Large Workstation Kitchen Sink - Single Bowl - Reversible
Offset Drain (5LS40c) or equivalent. 1 big stainless steel sink total.
110 22 42 39 00 0025 EA Single Handle Centerset Lavatory Faucet, Polished Chrome Finish (Delta 638.68
Lahara 538-MPU-DST)
Quantity Unit Price Factor Total
Installation
2.00
x
249.68 x 1.2790 638.68
Provide and install 2 new bathroom sink faucets in men's locker room at the new big sink. 2 faucets total. (This
faucet or equivalent)
111 22 42 39 00 0176 EA 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Angle Stop (SharkBite 77.43
23036)
Quantity Unit Price Factor Total
Installation =
2.00 x 30.27 x 1.2790 77.43
Provide and install 2 angle stop valves for breakroom relocation of plumbing. 2 valves total.
Subtotal for Division 22 (Plumbing) 6,606.96
Division 26 Electrical)
112 26 05 19 16 0205 MLF 4 Conductors, #12 AWG, Type MC, Solid Or Stranded, Galvanized Steel 4,168.40
Armored Cable
Quantity Unit Price Factor Total
Installation
0.83 x 3,950.43 x 1.2790 4,168.39
Provide and install approximately 825 feet of M/C cable required for rewiring of lights, j boxes, switches,
outlets, etc. 825 linear feet total.
Contractor's Price Proposal - Detail Page 11 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 26 (Electrical)
113 26 05 19 16 0246 EA 3/4" Armored Cable Connector 206.17
Quantity Unit Price Factor Total
Installation
40.00 x 4.03 x 1.2790 206.17
Provide and install approximately 40 connectors. 4o connectors total.
114 26 05 19 16 0246 0301 For Work In Restricted Working Space, Add 50.14
Quantity Unit Price Factor Total
Installation
40.00 x 0.98 x 1.2790
50.14
115 26 05 33 13 0014 CLF 3/4" Electrical Metallic Tubing (EMT) Conduit Assembly With 2 #10 Copper 954.95
THHN And 1 #12 Copper Insulated Grounding Conductorincludes conduit, set
screw connectors, set screw couplings, straps, wire as indicated. Not for use
where detail is available.
Quantity Unit Price Factor Total
Installation
1.20 x 622.20 x 1.2790 954.95
Provide and install approximately 120 linear feet of 3/4" EMT assembly. 120 feet total.
116 26 05 33 13 0014 0280 For Work In Restricted Working Space, Add 195.30
Quantity Unit Price Factor Total
Installation
1.20 x 127.25 x 1.2790 = 195.30
117 26 05 33 16 0005 EA 3-1/2" Depth, 4" Square Steel Box 799.06
Quantity Unit Price Factor Total
Installation
25.00 x 24.99 x 1.2790 799.06
Provide and install approximately 25 steel electrical boxes per plan for j-boxes above the ceiling, electrical
outlets at new walls in offices, small breakroom area, and large breakroom area. includes switches in new
offices. 25 steel boxes total.
118 26 05 33 16 0005 0484 MOD For Stud Bracket, Add 29.42
Quantity Unit Price Factor Total
Installation
20.00 x 1.15 x 1.2790 29.42
119 26 05 33 16 0009 EA 5/8" Depth, 1 Gang, 4" Square Steel Mud Ring 185.46
Quantity Unit Price Factor Total
Installation
20.00 x 7.25 x 1.2790
185.46
Provide and install 20 mud rings on boxes for switches and receptacles per plan. 20 mud rings total.
120 26 05 33 16 0024 EA One Duplex Receptacle, 4" Square Steel Exposed Work Cover 48.09
Quantity Unit Price Factor Total
Installation
5,00
x 7.52 x 1.2790 = 48.09
Provide and install 5 new steel work cover for new junction boxes in ceiling space. 5 steel covers total.
121 26 27 26 00 0005 EA 20 Amperes, 1 Gang, NEMA 5-20, Duplex Receptacle Assembly 860.26
Quantity Unit Price Factor Total
Installation
12.00 x 56.05
x 1.2790 - 860.26
Provide and install approximately 12 new receptacles in various added walls and breakrooms. 12 receptacles
total.
122 26 27 26 00 0009 EA 20 Amperes, 1 Gang, GFI, Duplex Receptacle Assembly 267.40
Quantity Unit Price Factor Total
Installation
3.00 x 69.69 x 1.2790
267.40
Provide and install 3 GFI plugs for the small breakroom. 3 GFI receptacles total.
123 26 27 26 00 0138 EA 1 Gang, 20 Amperes, 120/277 Volt, SPST, Switch Assembly 381.97
Quantity Unit Price Factor Total
Installation
5.00 x 59.73 x 1.2790 381.97
Provide and install approximately 5 new switch assemblies. 5 switch assemblies total.
Contractor's Price Proposal - Detail Page 12 of 13
8/6/2025
Contractor's Price Proposal - Detail Continues..
Work Order Number: 146114.00
Work Order Title: Anna - Public Works Building Reno
Division 26 (Electrical)
124 26 51 19 00 0039 EA 2' x 4', 4,600 Lumens, Prismatic Lensed, Lay-In/Troffer LED Fixture (Lilhonia $388.20
2TL4)
Quantity Unit Price Factor Total
X Installation
8.00 x 37.94 x 1.2790 388.20
Reinstall 8 existing lights to accommodate several new office areas. 8 lights reworked total.
125 26 51 19 00 0039 EA 2' x 4% 4,600 Lumens, Prismatic Lensed, Lay-In/Troffer LED Fixture (Lithonia $1,470.95
2TL4)
Quantity Unit Price Factor Total
Installation
2.00
x 575.04 x 1.2790 - 1.470.95
Provide and install 2 new light fixtures per plan. 2 new lights total.
Subtotal for Division 26 (Electrical) $10,005.77
Proposal Total $164,238.33
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
Contractor's Price Proposal - Detail Page 13 of 13
8/6/2025
Subcontractor Listing
Date: August 06, 2025
Re: IQC Master Contract #:
Work Order #:
Owner PO #:
Title:
Contractor:
Proposal Value:
TX-R3-GC-052124-SCL
146114.00
Anna - Public Works Building Reno
Structured Construction LLC
164, 238.33
GOPDIAN(,",
Name of Contractor Duties Amount
No Subcontractors have been
selected for this Work Order
0.00 0.00
Subcontractor Listing Page 1 of 1
8/6/2025
N STRUCTURED
C 0 N S T R U C T 1 0 N
SCOPE OF WORK
The City of Anna
Public Works Building - Anna, TX
Public Works Building Renovation
0810512025
This Scope of Work describes the Public Works Building Renovation Project at the Public Works
Building in Anna, TX. Public Works Building to be performed by Structured Construction LLC
Structured") as the general contractor. Work includes Safety/General Requirements (Div. 01),
Existing Conditions (Div. 02), Metals (Div. 05), Openings (Div. 08), and Finishes (Div. 09),
Furnishings (Div. 12), Plumbing (Div. 22), and Electrical (Div. 26). The repairs will be phased, as
required, to accommodate Anna's Public Works personnel.
1.0 SCOPE OF WORK:
The scope of work to be performed by Structured includes all labor, materials, supervision,
equipment, insurance, taxes, and overhead costs necessary to perform the work described herein.
Work includes the following:
1.1 Public Works Building Renovation
1. Brief SOW: Demo flooring, walls, electrical, plumbing, millwork, and install all described
finishes, electrical, plumbing, etc..
1.1.1 Division 01 - Safety/General Requirements:
Work includes the following:
Provide 4 - 30 yard dumpsters for debris removal from site. 4 dumpsters total.
Provide and install approximately 4152.3 square feet of 6 mil plastic to protect all of the
ceilings. 4152.3 square feet total.
1.1.2 Division 02 - Existing Conditions:
Work includes the following:
Demo and dispose of approximately 1644.4 linear feet of resilient baseboard. 1644.4 linear
feet total.
Demo and remove approximately 2971.5 square feet of VCT per plan. 2971.5 square feet
total.
Demo and dispose of approximately 129 square feet of ceramic tile flooring in the entry
way. 129 square feet total.
Demo and remove approximately 320.8 square yards of existing carpet. 320.8 square yards
total.
Demo and dispose of approximately 129 square feet of thin set for the old ceramic tile in
the front entry. 129 square feet total.
Demo 2 existing door frames per plan. Salvage 1 liM frame only, dispose of the other
wood frame. 2 total.
Demo and salvage of 1 existing solid core door. 1 total.
Demo and remove approximately 264 square feet of existing epoxy flooring. 264 square
feet total.
Demo and remove approximately 24 square feet of countertop per plan in front lobby. 24
square feet total.
Demo and dispose of approximately 30 connectors. 30 connectors total.
Remove 1 lockset/door knob and salvage to reinstall on salvaged door. 1 total.
Demo and remove existing glass window. Approximately 4 square feet window 24" x 24".
Demo and remove existing countertop in men's locker room. Approximately 12 square feet
total.
Demo and Remove existing 2 sinks in mens locker room. 2 sinks removed total.
Remove and reinstall base cabinets in big break room into small break room. 18 linear feet
total.
Remove and reinstall upper cabinets in big break room into small break room. 18 linear
feet total.
Remove and reinstall countertops in big break room into small break room. 18 linear feet
total.
Demo and remove 3 - 36" wide base cabinets in small breakroom. 3 base cabinets total.
Demo and remove 1 - 48" wide base cabinet in small breakroom. 1 base cabinet total.
Demo and remove 4 - 36" wide wall cabinets in small breakroom. 4 wall cabinets total.
Demo and remove 1 - 12" wide wall cabinet in small breakroom. 1 wall cabinet total.
Demo and remove approximately 9 square feet of existing countertops in small break room
area. 9 square feet total.
Demo and remove 20 linear feet of existing copper tubing per plan in small break room. 20
linear feet total.
Demo and remove approximately 4 - 1/2" 90's per plan. 4 - 90's total.
Demo and remove approximately 2 - 1/2" copper tees in small breakroom area. 2 total.
Demo and remove 2 - %" angle valves in small breakroom. 2 angle valves total.
Demo and remove approximately 20 linear feet of pvc pipe in small breakroom area. 20
linear feet total.
Demo and remove 2 sinks in men's locker room. 2 sinks total.
Demo and remove 4 - 1/2" copper couplings in small breakroom. 4 couplings total.
Demo and remove approximately 15 electrical boxes per plan in offices, small breakroom
area, and the large breakroom area. 15 steel boxes total.
Demo and remove approximately 120 linear feet of existing 3/4" EMT per plan. 120 linear
feet total.
Demo and remove approximately 600 linear feet or armored cable per plan. 600 linear feet
total.
Remove and salvage approximately 8 existing light fixtures. 8 lights total.
Demo and remove 2 - 2" pvc 90's in small breakroom. 2- 90's total.
Demo and remove 1 - 2" pvc sanitary tee in small breakroom. 1 tee total.
Demo and remove 2 existing p-traps from men's locker room and small break room.
Demo and remove 2 - 2" wye's in small breakroom. 2 wye's total.
Demo and remove 1 - 2" cleanout tee in small breakroom. 1 cleanout tee total.
Demo and remove approximately 30 cubit feet of existing slab to open up the slab to run
new plumbing in the small breakroom. 30 cubit feet total.
Sawcut approximately 55 linear feet of existing concrete slab to install new plumbing in the
small breakroom. 55 linear feet total.
1.1.3 Division 05 - Metals:
Work includes the following:
Provide and install approximately 40 linear feet of square tubing to be fabricated into a
frame for the new men's locker room sink. 40 linear feet total.
Provide welder to fabricate metal frame to be hung on the wall in men's locker room for
new big sink. includes installation of frame. This includes time for shop drawings/design,
shop fabrication and onsite installation onsite. 24 hours total.
1.1.4 Division 08 - Openings:
Work includes the following:
Provide and install 1 new 36" x 36" aluminum sliding glass window at lobby per plan. 1
sliding glass window total.
Provide and install 3 doors per plan. 3 doors total.
Provide and install three 3' x T HM door frames per plan. 3 total.
Reinstall 1 salvaged lockset/door knob. 1 lockset total.
Provide and install 3 lockets per plan. 3 locksets total.
Provide and install 2 sets (3 per set) of hinges per plan. 1.5 hinges x 2 doors = 3 hinge pairs
total.
1.1.5 Division 09 - Finishes:
Work includes the following:
Perform first moisture test for new LVT flooring required for flooring warranty. 1 primary
test total.
Perform 6 moisture tests for new LVT flooring required for flooring warranty. One
secondary test is required per 1,000 square feet. 6 secondary tests total.
Provide and install approximately 3145.7 square feet of a'/8" self leveling underlayment for
new LVT flooring. 50% coverage. 3145.7 square feet total.
Demo and remove approximately 101.2 square feet of walls per plan. 101.2 square feet
total.
Provide and install approximately 616.8 square feet of new metal stud walls per plan. 618.8
square feet total.
Provide and install approximately 1233.6 square feet tape, spackle and wall finish per plan.
1233.6 square feet total. No texture will be applied to new walls, smooth finish only.
Provide and install approximately 1644.4 linear feet of new rubber baseboards throughout
entire space. 1644.4 linear feet total.
Patch approximately 511 square feet of wall in various locations to prep for paint. 511
square feet total.
Provide and install approximately 1233.6 square feet Type X gypsum board per plan.
1233.6 square feet total.
Provide and install 2 coats of paint for approximately 6490 square feet on all walls inside
new space per plan. 6490 square feet total.
Provide and install 1 coat of primer for approximately 6490 square feet on all walls inside
new space per plan. 6490 square feet total.
Rework existing ceilings tiles to accommodate new wall that goes above ceiling in the
lobby. Approximately 30 square feet total.
Rework ceiling grid in lobby at new wall that goes above ceiling. Approximately 30
square feet total.
Provide and install 1 coat primer for 2 new FM door frames per plan. 34 linear feet total.
Provide and install 2 coats paint for 2 new HM door frames per plan. 34 linear feet total.
Provide and install 1 coat primer for 2 new wood doors per plan. 2 doors total.
Provide and install 2 coats paint for 2 new wood doors per plan. 2 doors total.
Provide and install approximately 6291.3 square feet of new LVT flooring throughout the
entire space. 6291.3 square feet of flooring total.
Demo and remove approximately 93.2 linear feet of transition striping per plan. 93.2 linear
feet total.
1.1.6 Division 12 - Furnishings:
Work includes the following:
Provide and install one cutout for big sink in men's locker room new solid surface
countertop. 1 cutout total.
Provide and install new men's locker room sink solid surface countertop end splash guard.
Approximately I linear feet total.
Provide and install new men's locker room sink solid surface countertop. Approximately 12
square feet total.
1.1.7 Division 22 - Plumbing:
Work includes the following:
Provide and install one undermount 40" to 48" Large Workstation Kitchen Sink - Single
Bowl - Reversible Offset Drain (5LS40c) or equivalent. 1 big stainless steel sink total.
Provide and install 2 new bathroom sink faucets in men's locker room at the new big sink. 2
faucets total. (This faucet or equivalent)
Hours for plumber to rework plumbing (drains and waterlines) underneath new big sink in
men's locker room. 16 hours total.
Provide and install 60 linear feet of 1/2" copper pipe for small breakroom plumbing
relocation. 60 linear feet total.
Provide and install twelve 1/2" copper 90's for small breakroom plumbing relocation. 12 -
90's total.
Provide and install two 1/2" copper tees for small breakroom plumbing relocation. 2 tees
total.
Provide and install four 1/2" copper couplings for small breakroom plumbing relocation. 4
couplings total.
Provide and install 2 angle stop valves for breakroom relocation of plumbing. 2 valves
total.
Provide and install approximately 60 linear feet of 2" DWV PVC pipe for small breakroom
relocation of plumbing. 60 linear feet total.
Provide and install four 1/2" copper caps for small breakroom plumbing relocation. 4 caps
total.
Provide and install 4 - 90's for small breakroom relocation of plumbing. 4 - 90's total.
Provide and install 1 sanitary tee for small breakroom relocation of plumbing. 1 sanitary tee
total.
Provide and install 2 wyes for small breakroom relocation of plumbing. 2 wyes total.
Provide and install 1 test tee with plug for small breakroom relocation of plumbing. 1 test
tee total.
1.1.8 Division 26 - Electrical:
Work includes the following:
Provide and install approximately 12 new receptacles in various added walls and
breakrooms. 12 receptacles total.
Provide and install approximately 25 steel electrical boxes per plan for j-boxes above the
ceiling, electrical outlets at new walls in offices, small breakroom area, and large
breakroom area. includes switches in new offices. 25 steel boxes total.
Provide and install 5 new steel work cover for new junction boxes in ceiling space. 5 steel
covers total.
Provide and install 20 mud rings on boxes for switches and receptacles per plan. 20 mud
rings total.
Provide and install 3 GFI plugs for the small breakroom. 3 GFI receptacles total.
Provide and install approximately 120 linear feet of 3/4" EMT assembly. 120 feet total.
Provide and install approximately 825 feet of M/C cable required for rewiring of lights, j
boxes, switches, outlets, etc. 825 linear feet total.
Provide and install approximately 40 connectors. 40 connectors total.
Provide and install approximately 5 new switch assemblies. 5 switch assemblies total.
Provide and install 2 new light fixtures per plan. 2 new lights total.
Reinstall 8 existing lights to accommodate several new office areas. 8 lights reworked total.
2.0 SPECIFICATIONS:
As provided by City of Anna Personnel and are described in the scope of work.
2.1 DRAWING AND SKETCHES:
Sketches and drawings not provided.
2.2 SPECIFICATIONS:
Work shall be performed per the latest edition of the applicable federal, state, and local codes and
standards.
3.0 SUBMITTALS:
Structured shall submit the indicated number of copies of each required submittal. Submittals shall
be submitted and approved prior to incorporating that material or activity into the project. Submittals
required by specification and/or drawings shall be made regardless of whether or not they are listed
on this schedule.
3.1 SUBMITTAL TYPE AND DESCRIPTION OUTLINE:
Type Description Tvve Descri tion
A Shop Drawings F Notification of Sample Availability
B Manufacturer's Catalog Cuts/Data G Application Instructions
C Certificate/Certification H Operations & Maintenance O&M Manuals
D Performance Test Reports I Color Samples
E Sample of Testing J Red Line Drawings
3.2 PROJECT SUBMITTAL REQUIREMENTS:
Required Submittal
4.0 SPECIAL CONSIDERATIONS:
Special considerations are applicable to this project as outlined in the following:
4.1 Structured will contact the customer project manager to coordinate scheduled equipment outages if
required.
4.2 Normal working hours for this project are Monday through Friday 8:00 am — 5:00 pm. Working
outside of normal working hours or on holidays will be coordinated and approved by the customer. The
scope of work does not include the cost of work outside of normal working hours unless noted.
4.3 All work performed shall be in accordance with the applicable requirements of the latest edition of
the Occupational Safety and Health Act (OSHA), Structured safety requirements and customer procedures
as provided to Structured.
4.4 This proposal is valid for 28 days.
5.0 Exclusions:
The following items are excluded from the scope of work:
1. Asbestos or lead abatement
2. SWPPP
3. Anything not specified in the above scope of work.