HomeMy WebLinkAboutRes 2009-10-02 Accepting Tank Builders-1.5 Mil Gal Ground Storage Tank as complete.pdfCITY OF ANNA, TEXAS
RESOLUTION NO. 2009-10-02
A RESOLUTION BY THE CITY COUNCIL OF THE CITY OF ANNA ACCEPTING THE
CONTRACT WITH TANK BUILDERS, INC. FOR THE CONSTRUCTION OF THE
SOUTH PLANT 1.5 MIL. GAL. GROUND STORAGE TANK FOR THE CITY OF ANNA
PROJECT AS COMPLETE
WHEREAS, the city of Anna has entered into a Contract for Water Supply and Sewer
Service with the Greater Texoma Utility Authority; and
WHEREAS, the Greater Texoma Utility Authority has entered into a contract with Tank
Builders, Inc. for the construction of the South Plant 1.5 Mil. Gal. Ground Storage Tank project for
the City of Anna; and
WHEREAS, representatives of the City of Anna, the Greater Texoma Utility Authority,
and the consulting engineer have reviewed the facility constructed as the South Plant 1.5 Mil. Gal.
Ground Storage Tank project and found it to be complete;
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF ANNA that the city hereby formally accepts the work ofTank Builders, Inc. as complete.
Upon motion by Council Member Keith Green, seconded by Council Member Mike Crist,
the foregoing Resolution was passed and approved on this 13th day of October, 2009 by the
following vote:
AYE: 7 NAY: 0 ABSTAIN: 0
At a regular meeting ofthe City Council of Anna.
ATfEST:
Res. 2009-10-02 Accepting Tank Builders contract complete.doc 1 10-13-09