HomeMy WebLinkAboutRes 2023-10-1559 Amending the Advanced Funding Agreement- TxDot-Ferguson Pkwy ProjectCITY OF ANNA, TEXAS
RESOLUTION NO. '���3 • I O — 5 rJq
A RESOLUTION OF THE CITY OF ANNA, TEXAS, APPROVING AND AUTHORIZING
THE CITY MANAGER TO EXECUTE AN AMENDMENT TO THE ADVANCE FUNDING
AGREEMENT BY AND BETWEEN THE CITY OF ANNA, TEXAS, AND THE TEXAS
DEPARTMENT OF TRANSPORT FOR FERGUSON PARKWAY, WITH AN EFFECTIVE
DATE.
WHEREAS, the State and the Local Government executed a contract on March 5, 2021,
to effectuate their agreement for the reconstruction and widening of a 2-lane roadway to
a 4-lane urban divided roadway, with future widening to a 6-lane urban divided roadway,
that will include new sidewalks and the construction of a 6-lane bridge over Slayter Creek
along Ferguson Parkway from Elm Street to the Collin County Outer Loop in the City of
Anna; and
WHEREAS, the federal and state laws require local government to meet certain contract
standards relating to the management and administration of state and federal funds; and
WHEREAS, the Advanced Funding Agreement approved by this resolution sets forth the
cost -sharing for the Project using federal, state, and local funds and other obligations of
the parties:
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ANNA, TEXAS, THAT:
Section 1. Recitals Incorporated
The recitals above are incorporated herein as if set forth in full for all purposes.
Section 2. Approval of Amendment #1 of the Advanced Funding Agreement
The City Council of the City of Anna, Texas, hereby approves Amendment number one
to the Advanced Funding Agreement For Surface Transportation Block Grant Program
Project Off -System ( Advanced Funding Agreement) by and between the City of Anna,
Texas, and the State of Texas, acting by and through the Texas Department of
Transportation, and authorizes, ratifies and approves the City Manager's execution of the
amendment number one to the Advanced Funding Agreement on behalf of the City of
Anna, Texas.
PASSED AND APPROVED by the City Council of the City of Anna, Texas on this Ltd
day of October 2023.
ATTEST:
City Secretary, Carrie Land
APPROVED:
layor, Nate Pike
MOT: Federal Highwav Administration:
CSJ # 0918-24-249 CFDA No. 20.205
District # 18- Dallas FA ID 00001962 CFDA Tile Highway Planning and Construction
Code Chart64 # 01300
Project Name Ferguson Parkway AFA Not Used For Research & Development
STATE OF TEXAS §
COUNTY OF TRAVIS §
ADVANCE FUNDING AGREEMENT
AMENDMENT#1
THIS AMENDMENT is made by and between the State of Texas, acting through the Texas
Department of Transportation, called the State, and the City of Anna, acting by and through it's duly
authorized officials, called the Local Government.
WITNESSETH
WHEREAS, the State and the Local Government executed a contract on March 5 of 2021 to
effectuate their agreement for the reconstruction and widening of a 2-lane roadway to a 4-lane urban
divided roadway, with future widening to a 6-lane urban divided roadway, that will include new
sidewalks and the construction of a 6-lane bridge over Slayter Creek along Ferguson Parkway from
Elm Street to The Collin County Outer Loop in the City Anna and,
WHEREAS, it has become necessary to amend that contract;
NOW THEREFORE, in consideration of the premises and of the mutual covenants and agreements
of the parties, the State and the Local Government do agree as follows:
AGREEMENT
1. Description of Amended Items
A. Attachment C. Project Budget Estimate and Source of Funds of the original agreement
is deleted in its entirety and replaced with:
Attachment C-1. Project Budget Estimate and Source of Funds which is attached to
and made part of this agreement. The total contract amount is increased by $1,804,735
from $1,072,481 to $2,877,216.
All other provisions of the original contract are unchanged and remain in full force and effect.
2. Signatory Warranty
Each signatory warrants that the signatory has necessary authority to execute this agreement on
behalf of the entity represented.
AFA Amend Page 1 of 2 Revised 11/9/2021
ixDOT: Federal HI way Administration:
-SJ # 0918-24-249 CFDA No. 20205
district It18- Dallas FA ID 00001962 CFDA Title HI.hwa Planning and Construction
ode Chart64 # 101300
3"o ect Name I Ferguson Parkway AFA Not Used For Research & Development
Each party is signing this amendment on the date stated under that party's signature.
THE LOCAL GOVERNMENT
Signature
Ryan Henderson
Typed or Printed Name
CitV Manager
Title
Date
THE STATE OF TEXAS
N
AFA Amend Page 2 of 2 Revised 11/9/2021
TXDOT:
CSJ# 0918-74-249
District # 118. Dallas AFA ID Z00001962
Code Chart 64 # 1 01300
Project Name I Ferguson Parkway from Elm Street to
the Collin County Outer Loop
Federal Highway Adminlstratlon:
CFDA No. 1 20.205
I CFDA Title I Highway Planning and Construction
AFA Not Used For Research 8 Development
ATTACHMENT C-1
PROJECTBUDGET
Preliminary engineering costs will be based on 80% Federal funding (Cat. 7) and 20% Local Government funding until Federal funding
reaches the maximum obligated amount. The Local Government will then be responsible for the cost of all project overruns.
DESCRIPTION
TOTAL
ESTIMATED
COST
FEDERAL
PARTICIPATION
STATE
PARTICIPATION
LOCAL
PARTICIPATION
°k
Cost
%
Cost
Cost
Environmental (by Local) Cat 7
$704 917
80%
$563 934
0%
$0
20%
$140,983
Engineering (by Local) Cat 7
$2 819,673
80%
$2 255.738
0%
$0
20%
$563,935
Subtotal
$3,524,590
$2,819672
$0
$704,918
Direct State Cost — Env
$17,982
80%
$14 386
0%
$0
20%
$3,596
Direct State Cost — Eng.
$17,982
80%
$14:386
0%
$0
20%
$3,596
Direct State Cost — ROW
$17,983
80%
$14,386
0%
$0
20%
1 $3,597
Direct State Cost — UTL
$17,983
80%
$14,386
0%
$0
20%
1 $3,597
Subtotal
$71,930
$57,544
$14,386
Indirect State Cost-4.73%
$166,713
0%
100% $166,713
0%
11 TOTAL
$3,596,520
$2,877, 116
$166,713
$719,304
Initial Payment by the Local Government to the State: $14,386.
Payment by the Local Government to the State prior to construction: $0.
Estimated total payment due by the Local Government to the State: $14,386.
This is an estimate. The final amount of Local Government participation will be based on actual costs.
Page 1 of 1
AFA LongGen Attachment C
UocuSign Envetope IU: 3USAC84U-CC38-4ESt-A/A1-L:6(i3bD6UB2US
Transportation Improvement Program Project Modification
PROJECT
District
TIP Code Highway County City Implementing MTP Reference(s)
Agency
DALLAS
14077 CS COLLIN ANNA ANNA BP2-002, M03-002. NRSA1-0AL-
309
Limits From:
FERGUSON PKWY FROM ELM STREET
Limits To:
THE COLLIN COUNTY OUTER LOOP
Project Scope:
CONSTRUCT 012 TO 4 LANE URBAN DIVIDED (6 LANES ULTIMATE), INCLUDING NEW SIDEWALKS AND 0 TO 6 LANE BRIDGE
OVER SLAYTER CREEK
FY
Phase
CSJ
Category
Federal
State Regional Local Local Total
Contribution
2021
ENG
0918-24-249
7 - STBG
$1,072,481
$0 $0 $268,120 $0 $1,340,601
2023
ENG
0918-24-249
7 - STBG
$1,748,319
$0 $0 $437,080 $0 $2,185,399
Total $2,820,800 $0 $0 $706,200 $0 0,526,000
PROPOSED MODIFICATION
PROJECT
District TIP Code Highway County city Implementing MTP Reference(s)
Agency
DALLAS
14077
CS COLLIN ANNA ANNA BP2-002, M03-002, NRSA1-DAL-
309
Limits From:
FERGUSON PKWY FROM ELM STREET
Limits To:
THE COLLIN COUNTY OUTER LOOP
Project Scope:
CONSTRUCT 0/2 TO 4 LANE URBAN DIVIDED (6 LANES ULTIMATE), INCLUDING NEW SIDEWALKS AND 0 TO 6 LANE BRIDGE
OVER SLAYTER CREEK
Comments:
AQ Statement: THIS PROJECT IS CONSISTENT WITH MOBILITY 2045 UPDATE AND THE RESULTING AIR QUALITY CONFORMITY ANALYSIS
FY Phase CSJ Category Federal State Regional Local Local Total
Contribution
2021
ENG 0918-24-249 7-STBG
$1,072,481
$0
$0
$268,120
$0
$1,340,601
2024
ENG 0918-24-249 7-STBG
$1,804,735
$0
$0
$451,184
$0
$2,255,919
Total
$2,877,216
$0
$0
$719,304.
$0
$3,696,b20
No - Contingent on TxDOT approval? The following signature authorizes:
No -Additional MPO Allocated Funds Moved to Year One
No - Modification to TxDOT Selected Program
C DoBtitMnn CERTIFIED BY:
ClwnyNe 7/18/2023
N/A
Christie th Date
Senior Program Manager
NCTCOG
THE CITY OF
Anna
Z-�Ito -155Ci
Item No. 7.a.
City Council Agenda
Staff Report
Meeting Date: 10/10/2023
Staff Contact: Justin Clay
AGENDA ITEM:
Consider/Discuss/Action on Amendment One to the Advanced Funding Agreement by
and between the City of Anna, Texas and the Texas Department of Transportation for
the Ferguson Parkway Project. (CIP Manager Justin Clay)
SUMMARY:
This item will authorize the City Manager to execute an amendment to the existing
Advanced Funding Agreement between the State of Texas and the City of Anna for the
environmental and engineering design scope of the Ferguson Parkway project from Elm
Street to the Collin County Outer Loop. The original agreement was approved by the
City Council via Resolution 2021-02-865. The scope of work required for the
environmental study and design has increased, requiring the Advanced Funding
Agreement to be revised. The North Central Texas Council of Governments has agreed
to fund their full 80% match of the increase, with the City being responsible for 20% of
the cost. This agreement represents excellent value to Anna neighbors, as the
partnership results in the design of a major project with the City only being responsible
for 20% of the cost.
FINANCIAL IMPACT:
Funding for the Engineering Design of Ferguson Parkway project was appropriated in
the FY2023 Community Investment Program budget in the amount of $719,304 from the
Roadway Impact Fee Fund. The project funding is an 80%/20% match with the North
Central Texas Council of Governments. The estimated city portion of the design project
cost is $719,305. The North Central Texas Council of Governments portion of the
project cost is $2,877,216.
BACKGROUND:
Ferguson Parkway is included in the City of Anna Master Thoroughfare Plan as a major
arterial roadway.
STRATEGIC CONNECTIONS:
This item supports the City of Anna Strategic Plan, specifically advancing the strategic
outcome area: Resilient.
ATTACHMENTS:
1. AFA Agreement Resolution
2. 0918-24-249 City of Anna Ferguson Pkwy AMENDMENT
3. TIP MOD #2 August 2023 Signed
4. Original AFA - Res 2021-02-865 STBG Anna and TxDOT