RESOLUTION NO. 2 O 2 t4 — O(o - 1(o3cj'
A RESOLUTION OF THE CITY OF ANNA, TEXAS, AUTHORIZING THE CITY
MANAGER TO EXECUTE A CONTRACT WITH WSB ENGINEERING FOR
MATERIALS TESTING ON THE HURRICANE CREEK WASTEWATER
INTERCEPTOR PHASE ONE PROJECT IN AN AMOUNT NOT TO EXCEED SEVENTY
THOUSAND DOLLARS AND ZERO CENTS. ($70,000.00); AND PROVIDING FOR AN
EFFECTIVE DATE.
WHEREAS, the Hurricane Creek Wastewater Interceptor is listed as a capital
improvement project in the City of Anna's Capital Improvement Plan; and,
WHEREAS, the proposed material testing is required for the construction of the Hurricane
Creek Interceptor and to ensure proper backfill compaction and concrete testing
associated with the project; and,
WHEREAS, Utility bond funds shall be used to fund the contract in an amount not to
exceed $70,000.00.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ANNA, TEXAS, THAT:
Section 1. Recitals Incorporated
The recitals above are incorporated herein as if set forth in full for all purposes.
Section 2. Authorization of Payment and Funding.
That the City Council of the City of Anna hereby authorizes the City Manager to execute
a contract in an amount not to exceed $70,000.00 to WSB Engineering for the material
testing of the Hurricane Creek Regional Wastewater Interceptor Phase One Project
That funding for the project shall come from the Wastewater Impact Fees and shall not
exceed $70,000.00.
PASSED AND APPROVED by the City Council of the City of Anna, Texas, on this a 5 *�
day of June 2024.
ATTEST:
City Secretary, Carrie Land
APPROVED:
M yor, Pete Cain