HomeMy WebLinkAboutRes 2012-10-05 General Eng Serv for Sewer System.pdfCITY OF ANNA, TEXAS
RESOLUTION NO. 2012-10-05
A RESOLUTION OF THE CITY OF ANNA, TEXAS APPROVING AND AUTHORIZING THE
CITY MANAGER TO ACT ON THE CITY'S BEHALF IN EXECUTING A GENERAL
ENGINEERING SERVICES — TASK AUTHORIZATION FOR SEWER SYSTEM
IMPROVEMENTS
WHEREAS, the City Council ("City Council") of the City of Anna, Texas ("City") has
determined that the City is need of hiring an engineering firm to provide general engineering
services to assist the City in its governmental functions to benefit the health, safety and
welfare of the citizens and the general public; and
WHEREAS, the City Council has previously determined, based on submissions received
from various engineering firms, that the most highly qualified provider of such services on
the basis of demonstrated competence and qualifications was Birkhoff, Hendricks & Carter,
L.L.P.; and
WHEREAS, with the growth that is now occurring in the city, it will soon be necessary to
construct certain improvements to the wastewater collection system; and,
WHEREAS, staff has received a Task Authorization from Birkhoff, Hendricks & Carter, L.L.P.,
for the design of construction plans for the required sewer system improvements; and,
WHEREAS, money expended to pay for engineering services prior to the issuance of the
project bonds would be reimbursed to the Water & Sewer fund balance;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ANNA, TEXAS, THAT:
Section 1. Recitals Incorporated.
The recitals above are incorporated herein as if set forth in full for all purposes.
Section 2. Approval of General Engineering Services — Task Authorization.
The City Council hereby approves the General Engineering Services — Task Authorization
for sewer system improvements attached hereto as Exhibit 1, and authorizes, ratifies and
approves the City Manager's execution of same. The City Manager is hereby authorized to
execute all documents and to take all other actions necessary to finalize, act under, and
enforce the Task Authorization.
RES. General Eng. Serv. For Sewer Sustem Improvements PAGE 1 OF 2 10-09-12
PASSED AND APPROVED by the City Council of the City of Anna, Texas, on this 9t" day of
October, 2012.
ATTEST: APPROVES: f _
Nat a WI kison, City Secretary Mayor, Mi
RES. General Eng. Serv. For Sewer Sustem Improvements PAGE 2 OF 2 10-09-12
BI OFF, HENDRICKS & CARTER, L.L.P.
PROFESSIONAL ENGINEERS
11910 Greenville Ave., Suite 600 Dallas, Texas 75243
JOHN W. BIRKHOFF, P.E.
GARY C. HENDRICKS, P.E.
JOE R. CARTER, P.E.
PAUL A. CARLINE, P.E.
MATT HICKEY, P.E.
ANDREW MATA, JR., P.E.
JOSEPH T. GRAJEWSKI, III, P.E.
Mr. Philip Sanders
City Manager
City of Anna
111 North Powell Parkway
Anna, Texas 75409
Re: General Engineering Services — Task AuthorizationOrder
Slayter Creek Interceptor Sewer
Dear Mr. Sanders:
Fax (214) 461-8390 Phone (214) 361-7900
September 29, 2012
In accordance with your request and our existing general engineering services agreement, we are pleased to
submit this General Services Task AuthorizationOrder letter for services related to the preparation of
specifications, bidding documents and contract administration for the Slayter Creek Interceptor Sewer, from
the Throckmorton Creek Meter Station to the Slayter Creek Wastewater Treatment Plant.
GENERAL PROJECT DESCRIPTION
This project consists of the construction of the 18 -inch diameter Slayter Creek Interceptor Sewer from the
Throckmorton Creek Meter Station to the Slayter Creek Wastewater Treatment Plant. The project goal is to
provide a relief interceptor sewer for the Slayter Creek Wastewater Treatment Plant which will convey
sanitary sewer flows in excess of the treatment plant permitted capacity into the North Texas Municipal Water
District's Upper East Fork Regional Interceptor System.
The project location map is attached as Exhibit A shows the general project route and limits.
Based on our understanding of the project requirements, our opinion of probable project budget is
summarized below:
Opinion of Probable Construction: $745,525
Quality Control and Materials Testing (2.5%): $ 18,650
Construction Inspection Services (2.5%): $ 18,650
Basic Engineering and Additional Services: $1465100
Land Rights Acquisitions(2.5 acres): 61,000
Total Project Budget: $989,925
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 2 of 9
A copy of our itemized opinion of cost is attached as Exhibit B.
SCOPE of SERVICES
Part I: Preliminary Engineering Report
Prepare a preliminary engineering report that re -confirms or revises the assumptions, evaluation, conclusions
and recommendations as presented to Anna City Council on February 28, 2012 and again on September 25,
2012. The engineering report will establish the recommended route, re -confirm pipe size and capacity;
determine easement requirements and identify property owners; and provided updated opinions of project cost.
Part II: Design Phase
Preparation of construction plans, specifications, bidding phase services and construction
administration phase services for the following:
A. Construction Plan -Profile Sheets prepared at a scale of not less than 1"= 20'.
B. Standard Details.
C. Special Details.
D. Cover Sheet, Location Map and Sheet Index.
E. Submittals to State Regulatory Agencies, as required.
F. Preparation of required Texas Department of Transportation permits, as required.
G. Coordination with other Franchise Companies.
H. 2 -Design review meetings.
I. Opinion of Probable Construction Estimate.
J. Preparation of Specifications and Contract Documents.
K. Assist in procuring geotechnical engineering information or reports as the project
requirements dictate.
L. Printing of preliminary plans and specifications for review by the City.
Part III: Bidding Phase
A. Assist the City staff in advertising for bids. This will include e -mailing "Notice to
Contractors" to contractors experienced in this type of construction. City will have
Notice published in local newspaper.
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
I:\city admin\administmtion\natha\city council\city council\2012\10-09-121item 8 - wastewater system improvements\item 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redline.docxl:\7015 contdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 3 of 9
B. Sell bidding documents to potential bidders and their suppliers and other parties.
C. Provide bidding documents to City of WaxahachieAnna, Dodge Reports, and two
other parties requested by the City.
D. Assist during opening of bids and provide bidding tally sheets.
E. Provide bid tabulation to City and contractors who submitted bids.
F. Obtain the following information from the lowest bidder:
1. Past work history.,
2. Physical resources to produce the project.
Formulate opinion from information received and provide the City a summary of
the opinion for their use in selection and award of the construction contract.
G. After award of contract, furnish ten sets of prints of the final plans, specifications
and contract documents to the City for construction use by the City and Contractor.
Part IV: Construction Phase
A. Attend a pre -construction conference, including preparing an agenda.
B. Attend coordination meetings with contractor, quality control personnel, and City
representatives to discuss strategy, problem areas, progress, and any required
coordination.
C. Review shop drawings and other submittal information, which the Contractor
submits. This review is for the benefit of the Owner and covers only general
conformance with information given by the Contract Documents. The contractor is
to review and stamp their approval on submittals prior to submitting to the
Engineer. Review by the Engineer does not relieve the Contractor of any
responsibilities, safety measures or the necessity to construct a complete and
workable facility in accordance with the Contract Documents.
D. Provide written responses to requests for information or clarification to City or
Contractor.
E. Prepare and process routine change orders for this project as they pertain to the
original scope of work.
F. Prepare monthly pay request from information obtained in the field.
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
1:\city admin\administration\natha\city council\city council\2012\10-09-12\item 8 - wastewater system improvements\item 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redline.docxl:\7015 cwntdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 4 of 9
G. Accompany the City during their final inspection of the project.
H. Recommend final acceptance of work based on information from the on-site
representative.
I. Prepare Record Drawings. Utilizing on-site representative and Contractor
construction record information, consultant will prepare one set of 22"x
34"reproducible record drawings on mylar and one set of electronic image files in
Adobe Acrobat file format.
Part V: Additional Services
A. Design, Property and Construction Surveys.
B. Preparation of Plat and Field Note Descriptions for expected drainage and/or utility
easements required for the project. Four (4) easement descriptions are included for
the purpose of establishing a budget for this phase of work.
C. Geotechnical evaluations and recommendations for the route selected. The
Geotechnical evaluation and report will be performed by a sub -consultant to be
approved by the City of Anna.
D. Printing of final plans and specifications for distribution to prospective bidders and
the successful contractor.
Part VI: Exclusions
The intent of this scope of services is to include only the services specifically listed herein and none
others. Services specifically excluded from this scope of services include, but are not necessarily
limited to the following:
A. Environmental impact statements and assessments.
B. Fees for permits or advertising.
C. Certification that work is in accordance with plans and specifications.
D. Environmental cleanup.
E. Landscape architecture.
F. Flood plain reclamation plans.
G. Trench safety designs.
Texas American Public Works Association 2010 Aivardee
Environmental Project of the Year $10 - $100 Million
(:\city admin\administration\natha\city council\city council\2012\10-09-12Utem 8 - wastewater system improvementAitem 8 - c03029 d20121004 slayter cr interceptor -task authorbation format
agreement erl redline.docxl:\7015 conldev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 5 of 9
H. Quality control and testing services during construction.
I. Services in connection with condemnation hearings.
J. Phasing of Contractor's work.
K. On-site safety precautions, programs and responsibility.
L. Consulting services by others not included in proposal.
M. Revisions and/or change orders as a result of revisions after completion of original
design (unless to correct error on plans).
N. Traffic engineering report or study.
O. Title searches
COMPLETION SCHEDULE
Notice to Proceed From City ............................................. October 1, 2012
Preliminary Engineering Report ......................................
October 15, 2012
Permission to Survey Obtained .........................................November
1, 2012
Submit Preliminary Plans to City for Review .................
January 1, 2013
Submit Plats and Field Notes for Easements: ....................
January 1, 2013
Complete Final Plans .......................................................
February 15, 2013
Land Rights Acquisitions: .................................................
By the City of Anna
Advertise Project for Bids (after land rights secured): ....
May 2, 2013
Receive Bids....................................................................
May 23, 2013
Award Construction Contract: ...........................................
June 4, 2013
Notice to Proceed with Construction: ................................
July 2, 2013
Construction Phase.......................................................... 12 months after notice to
proceed with construction
FEE NOT TO EXCEED AMOUNT
Basic Services
Payment for the Basic Services described under Parts I, II, III and IV, shall be on a Lump Sum Basis
in the following Amounts:
Part I Preliminary Engineering Report .................................................................$3,000
Part II Final Design Phase: ............................................................................... $69,000
PartIII - Bidding Phase: ....................................................................................... $2,500
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
(:\city admin\administmtion\natha\city council\city council\2012\10-09-12\item 8 - wastewater system improvements\item 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redtine.docAA7015 contdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 6 of 9
Part IV- Construction Phase........................................................................... $12,500
Total Amount, Basic Services (Parts I--1I11V):........... $879000
Additional Services
For the Additional Services described in Part V, we propose to be compensated on a salary cost basis
times a multiplier of 2.3 5, with expenses at actual invoice cost times 1.10. Automobile mileage for
special services will be invoiced at $0.50 per mile.
We suggest you budget approximately $ 59,100 in the following amounts for our services for this
project:
A. Design, Boundary and Construction Control Surveys ......................... $34,600
B. Preparation of Plats and Field Note Descriptions (4 each): ....................... $8,000
C. Geotechnical Evaluation and report: ....................................................... $15,000
D. Printing of Final Plans and Specifications ............................................. $1,500
Total Amount, Additional Services (Part M: .............. $59,100
Total Amount Not To Exceed:
$146,100
Texas Board of Professional Land Surveying Contact Information
Recipients of professional land surveying services under this agreement may direct complaints regarding such
services to the Texas Board of Professional Land Surveying, 12100 Park 35 Circle, Building A, Suite 156, MC
230, Austin, TX 78753, Phone (512) 239-5263, Fax (512) 239-5253.
If this General Engineering Services Agreement Task AuthorizationOrder meets with your approval, please
sign and return one set to our office along with your directive to proceed. We look forward to working with
you on this important project for the City of Anna and are available to discuss this task further at your
convenience.
Sincerely yours,
Gary C. Hendricks, P.E., R.P.L.S.
APPROVED FOR THE CITY OF ANNA, TEXAS
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
1:\city admin\administration\natha\city council city council\2012\10-09-12\item 8 - wastewater system improvements\item 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redline.docxl:\7015 cwntdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 7 of 9
Mr. Philip Sanders, City Manager Date
cc: Mr. Clark McCoy, Wolfe, Tidwell & McCoy, L.L.P.
Exhibit A - Project Location Map
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
1:\city admin\administration\natha\city council\city council\2012\10-09-12\ilem 8 - wastewater system improvements\item 8 - c03029 d20121004 slayter cr interceptor -task authorization formal
agreement crl redline.docxl:\7015 conldev\anna\2012 stayter creek interceptor sewer\.slayler cr interceptor -task authorization format agreement.doex Texas Firm F526
W Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 8 of 9
r
CR 367
PROPOSED 184NSWER
CH '
L NESANI (7,500 LEF. @
0.50% SLOPE)
Qca = 4.80 MGD 5
EXISTING
THROCKMORTON
CREEK METER
ETJ
, em law
WAL H nir
BERK <OFF, HENDRICKS & CARTER, L.L.P. CITY OF ANNA, TEXAS PRO ANO. SWFTNO.
PROPSSSIONALMOROMRS CAPITAL IMPROVEMENTS PROGRAM 4007-116
T...Finn F526 WASTEWATER COLLECTION SYSTEM ,)
Dail., Tex.Greenv752lle 43
(21) 361.79 SLAYER CREEK WWTP RELIEF LINE FEBRUARY 2012
Dallas, Tesas 75247 (214) 361.7900
rmxgu z{st/12 — 4ww\+mt �a s. .\ne —term tart x. am\�tm�.tn�aogar scvE tame KM smE --- ROM W. awn ON 2^12M
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
t:\city admin\administration\natha\city counciRcity council\2012\IO-09-12Utem 8 -wastewater system improvements\ilem 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redline.docxl:\7015 contdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526
Mr. Philip Sanders
General Services Task Authorization Order — Slayter Creek Interceptor Sewer
September 29, 2012
Page 9 of 9
Exhibit B — Opinion of Probable Project Cost
BI K OFF, HENDRICKS & CARTER, L.L.P. Project No. 4007-116
PROFESSIOIi.0 EI GLNEERS
Client: City of Via, Texas Ditel 14 -Sep -12
Proje-ctt Slayter Ceee Issterceptor Sewer
By. Gni
ENGINEER'S OPINION F CONSTRUCTION OST
Item BTU.
Description
Quantity
Unit
Price
I Amou t
1
ROW Preparation
75
Sta
$ 340.00
$ 22.504
2
Runish & Install 13 -inch Sanitary Sever Line by Open Ciit
7,500
L.F.
S 50.00
S 375,000
3
113 -inch Aerial Crossing (oT Siphon)
3
Ea
$ 25,004.04
$ 75,004
4
nnsh & Install 5 -Foot Dia �taudard Manhole
25
Ea
3.4
85,OypO,�Qr
5
��F^^u
Connect to fds:uaag -Inch SeiveT
4
Ea
6.00#
@$
$
6
+E. p6
Connect to Eyiscing, S -Inch `�a ita " Sew:�er
Sanitary
4
Ea
g$ ,755..p0.00
� 1.400/.00
_"�JSV,0
S 4..004
Connect to E=isdag ITanhole
2
Ea
1,000.44
s 2,004
-3
Rumish & histal! Hydromcdch Seeding
16,667
S.Y.
5 3.40
50,004
.0
Runish&InstallTrench Safety Plan
I
Ea
5.000.00
5.000
10
Furnish& Install Trench Safety System
7,500
L.F.
2.50
18,754
11
Furnishing .Storax Water Pollution Prevewioa Plan
I
Es
S 14,0 }.00+
10,000
12
Iai leniewatiou of Stonn Water Rreentiorn Plan
7,500
L.F_
1.170
s 7,504
13
Co an to UM, 1°P Headwo&s and lb�y-p ass strucnue
I
LS
214,000.04
20,004
Construction Subtotal:
677,7.;@
Contingencies and Miscellineons Items
lVi
67,775
Construction Total:
S 745,S25
Land Acquisitious
2.13
Acres
25,0N-00
$ 60.692
Quality Control and Material Testing
2.5§:
18.638
C:{rn'5trti{tiibII TIISIPE{titiner°ti1{E§
2.5@'0
18,638
Engineerings Surveying, Easement Preparation
Protect Total,
USE.
146.100
989 593
5 990,00
Texas American Public Works Association 2010 Awardee
Environmental Project of the Year $10 - $100 Million
1:\city adminladministration\natha\city councillcity council\2012\10-09-12\item 8 - wastewater system improvementA tem 8 - c03029 d20121004 slayter cr interceptor -task authorization format
agreement crl redline.doexIA7015 contdev\anna\2012 slayter creek interceptor sewer\slayter cr interceptor -task authorization format agreement.docx Texas Firm F526