HomeMy WebLinkAboutRes 2013-05-01 Change Order 4- Parkscape.pdfCITY OF ANNA, TEXAS
RESOLUTION NO. 2013-05-01
A RESOLUTION OF THE CITY OF ANNA, TEXAS APPROVING AND AUTHORIZING THE
CITY MANAGER TO ACT ON THE CITY'S BEHALF IN EXECUTING AND APPROVING
CHANGE ORDER NO. 4 TO THE CONTRACT WITH PARKSCAPE CONSTRUCTION INC,
FOR SLAYTER CREEK PARK PHASE 11.
WHEREAS, on October 23, 2012, the City of Anna, Texas (the City) award a contract to
Parkscape Construction Inc. for Slayter Creek Phase 11 (the "Project"), and;
WHEREAS, during the course of construction City Staff has identified several changes that
need to be made to the Project (Installation of additional concrete trails to make logical
connections to splash pad, parking lot, tennis court, and an area of concrete between the ball
fields. Other needed concrete includes an additional Disc Golf Tee Box and three picnic table
pads. Other items within this change order includes an additional 20 feet of 21foot high
fence, labor for a parking lot drainage basin, and the remodel of a low water crossing to
facilitate storm water movement.), and the cost of these changes (Change Order No. 4) will
be $39,336.00, and;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ANNA, TEXAS, THAT:
Section 1. Recitals Incorporated.
The recitals above are incorporated herein as if set forth in full for all purposes.
Section 2. Approval of Change Order No. 4.
The City Council hereby approves Change Order 4 with Parkscape Construction Inc.,
attached hereto as Exhibit 1 and Exhibit 2 respectively; and authorizes, ratifies and
approves the City Manager's execution of same. The City Manager is hereby authorized to
execute all documents and to take all other actions necessary to finalize, act under, and
enforce the Change Orders.
PASSED AND APPROVED by the City Council of the City of Anna, Texas, on this 14th day
of May, 2013.
ATTEST: 7/7/
:/} �-
`\\�U%uuliilriu,,�
OF
/y
N ha Wilkison, i y Secretary ? C�; a"�' Mayor, Mike Crist
a
p ;
P
RES. 2013-05-01 Change Order 4 — Parkscape — Slayter9 se 11 PAGE 1 OF 1 05-14-13
Item No.
City Secretary's use only
Date of Issuance: JEffective Date:
Owner: City of Anna, TX
Project: Slayter Creek Park Phase II
Contract changes are approved as follows:
Description of changes: Installation of additional concrete trails to make logical
connections to splash pad, parking lot, tennis court, and an area of concrete between
the ball fields. Other needed concrete includes an additional Disc Golf Tee Box and
three picnic table pads. Other items within this change order includes an additional
20 feet of 21foot high fence, labor for a parking lot drainage basin, and the remodel of
a low water crossing to facilitate storm water movement.
Reason for Change Order: Park detailing to make the elements of Slayter Creek Park
more functional.
Attachments: Table detailing the description of the changes.
CONTRACT PRICING
Original Contract Amount including Add/Alternates:
$ 1,190,713.10
Net Increase from Previous Change Orders:
$ (133,620.66)
Contract Price Prior to this Change Order:
$ 1,057,092.44
Net Increase/Decrease of this Change Order:
$ 39,336.00
Contract Price with All Approved Change Orders:
$ 1,096,428.44
City of Anna, TX
By: Philip Sanders, City Manager
Date:
Please sign both copies; return one copy to:
c/o Maurice Schwanke
PO Box 776
Anna, TX 75409-0776
Parkscape Construction, Inc.
By: Cindy Craig
Date:
City of Anna, TX
Item No.
City Secretary's use only
CHANGE ORDER No. 4
Slayter Creek Park Phase II Improvements
City of Anna, Texas
5/8/2013
No.
Description of Scope Change
Cost
1
Install 1,332 sft. additional trail complete-
$ 6,327.00
2
Install 4 ea. 8' ramps, with curb and trail connections as required-
$ 4,900.00
3
Install 2 ea. 6' ramps, with curb and trail connections as required-
$ 3,000.00
4
Labor to install 100 If. of 12" pipe with one basin-
$ 3,125.00
5
Add 201f. of 21' tall fence-
$ 1,780.00
6
Low water crossing as per detail, including demo, concrete headwall,
$ 7,782.00
7
Install 3 ea. picnic table slabs, and 1 ea. disc golf tee slab-
$ 1,740.00
8
Install 2,235 sft. of additional trail at Splash Park-
$ 9,722.00
9
Bond-
$ 960.00
TOTAL
$ 39,336.00